CN105608637A - Substation equipment model topology-based wiring diagram automatic generation method - Google Patents
Substation equipment model topology-based wiring diagram automatic generation method Download PDFInfo
- Publication number
- CN105608637A CN105608637A CN201510948978.5A CN201510948978A CN105608637A CN 105608637 A CN105608637 A CN 105608637A CN 201510948978 A CN201510948978 A CN 201510948978A CN 105608637 A CN105608637 A CN 105608637A
- Authority
- CN
- China
- Prior art keywords
- wiring diagram
- automatic generation
- equipment
- device model
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010586 diagram Methods 0.000 title claims abstract description 36
- 238000000034 method Methods 0.000 title claims abstract description 20
- 238000010937 topological data analysis Methods 0.000 claims abstract description 10
- 239000000203 mixture Substances 0.000 claims description 4
- 238000004458 analytical method Methods 0.000 claims description 2
- 238000012423 maintenance Methods 0.000 abstract description 9
- 230000003247 decreasing effect Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 4
- 230000007812 deficiency Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/28—Databases characterised by their database models, e.g. relational or object models
- G06F16/284—Relational databases
- G06F16/285—Clustering or classification
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Engineering & Computer Science (AREA)
- Databases & Information Systems (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Physics & Mathematics (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Public Health (AREA)
- General Engineering & Computer Science (AREA)
- Data Mining & Analysis (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a substation equipment model topology-based wiring diagram automatic generation method. The method includes the following steps of: equipment model classification: the equipment models of a substation are classified and sorted according to different attributes of power system equipment; equipment model topological analysis: association relationships between the equipment models are analyzed out according to topological connections between the equipment models; and wiring diagram automatic generation: the automatic generation of a wiring diagram is carried out according to the types and association relationships of the equipment models of the substation. With the method of the invention adopted, automation maintenance personnel can be emancipated from tedious wiring diagram drawing manual operation, work burden can be decreased, error probability can be lowered, the efficiency and level of automated work such as system maintenance can be improved, and therefore, maximum economic and security benefits can be obtained.
Description
Technical field
The present invention relates to a kind of wiring diagram automatic generation method based on substation equipment model topology, belong to power system dispatching automation technique field.
Background technology
Along with development and the progress of technology, the upgrading work of automated system is also more and more frequent, and model and wiring diagram maintenance work huge in system generative process have become a large problem that perplexs automated maintenance personnel. Model part can carry out interoperability by CIM reference format at present, but wiring diagram part, due to the disunity of form and lack of standardization, or to regenerate by the method for manual drawing, therefore, must work out the method that wiring diagram generates automatically, to alleviate automated maintenance personnel's workload. By substation equipment model is classified and topological analysis, combing goes out the wiring relation between device model, then device model is carried out to autoplacement and line, the final wiring diagram that automatically generates, thereby automated maintenance personnel can be drawn handwork and free from loaded down with trivial details wiring diagram, alleviate work load, reduce error probability, improve efficiency and the level of the automated jobs such as system maintenance, thereby obtain maximum economy and safety benefit.
Summary of the invention
The object of the invention is to overcome deficiency of the prior art, a kind of wiring diagram automatic generation method based on substation equipment model topology is provided, solves the technical problem heavy by artificial drafting wiring diagram work load in prior art, error rate is high, operating efficiency is low.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: the wiring diagram automatic generation method based on substation equipment model topology, comprises the steps:
Step 1: device model classification: the device model of transformer station is carried out to taxonomic revision according to the different attribute of power system device;
Step 2: device model topological analysis: go out the incidence relation between each device model according to the topological linking parsing between device model;
Step 3: wiring diagram generates automatically: carry out the automatic generation of wiring diagram according to the kind of substation equipment model and incidence relation.
The concrete grammar of device model classification is as follows: first classify by station according to the difference of transformer station; Then in each transformer station, classify again according to electric pressure; Finally carry out again the classification of different models according to the difference of device type, also will classify according to the difference of the equipment mode of connection simultaneously.
The concrete grammar of device model topological analysis is as follows: be connected in sorted device model according to the topology between device model, adopt the methods analyst of iterative search analysis to there emerged a the wiring relation between device model, take out interval composition simultaneously.
Whether the concrete grammar that takes out interval composition is: according to the equipment of a partiting template, check in corresponding interval example and exist, the template abstracted information that record instance is corresponding.
The concrete steps that wiring diagram generates are automatically: the autoplacement that first carries out bus and interval, secondly instantiation drafting is carried out in interval, again put other equipment, finally according to wiring relation, equipment is connected to drafting, finally complete the automatic generation of wiring diagram.
Compared with prior art, the present invention reachesBeneficial effectBe:
By substation equipment model is classified and topological analysis, combing goes out the wiring relation between device model, then device model is carried out to autoplacement and line, the final wiring diagram that automatically generates, thereby automated maintenance personnel can be drawn handwork and free from loaded down with trivial details wiring diagram, alleviate work load, reduce error probability, improve efficiency and the level of the automated jobs such as system maintenance, thereby obtain maximum economy and safety benefit, it is integrated that the present invention can be applicable to the software of dispatch automated system software platform human-computer interaction interface part.
Brief description of the drawings
Fig. 1 is device model sorted logic figure.
Fig. 2 is device model topological analysis flow chart.
Fig. 3 is the abstract flow chart in interval.
Fig. 4 is that wiring diagram is drawn flow chart automatically.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described. Following examples are only for technical scheme of the present invention is more clearly described, and can not limit the scope of the invention with this.
Wiring diagram automatic generation method based on substation equipment model topology, comprises the steps:
Step 1:Device model classification: the device model of transformer station is carried out to taxonomic revision according to the different attribute of power system device. As shown in Figure 1, be device model sorted logic figure. The device model of lane database, first classify by station according to the difference of transformer station, then, in each transformer station, classify again according to electric pressure, next carry out again the classification of different models according to the difference of device type, also will classify according to the difference of the equipment mode of connection simultaneously.
Step 2:Device model topological analysis: go out the incidence relation between each device model according to the topological linking parsing between device model. Fig. 2 is device model topological analysis flow chart. From a bus of certain electric pressure, the equipment that search is associated stops in the time searching bus, outlet or winding, when search be single-ended equipment time also stop, otherwise just continue search, finally manage out the wiring relation between device model, form multiple intervals example simultaneously. Whether Fig. 3 is the abstract flow chart in interval, according to the equipment in a partiting template, check in corresponding interval example and exist, the template abstracted information that record instance is corresponding.
Step 3:Wiring diagram generates automatically: carry out the automatic generation of wiring diagram according to the kind of substation equipment model and incidence relation. Fig. 4 is that wiring diagram is drawn flow chart automatically. First the autoplacement that carries out bus and interval, then carries out instantiation drafting to interval, next puts other equipment, finally according to wiring relation, equipment is connected to drafting, finally completes the automatic generation of wiring diagram.
The above is only the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, do not departing under the prerequisite of the technology of the present invention principle; can also make some improvement and distortion, these improvement and distortion also should be considered as protection scope of the present invention.
Claims (5)
1. the wiring diagram automatic generation method based on substation equipment model topology, is characterized in that: comprise the steps:
Step 1: device model classification: the device model of transformer station is carried out to taxonomic revision according to the different attribute of power system device;
Step 2: device model topological analysis: go out the incidence relation between each device model according to the topological linking parsing between device model;
Step 3: wiring diagram generates automatically: carry out the automatic generation of wiring diagram according to the kind of substation equipment model and incidence relation.
2. the wiring diagram automatic generation method based on substation equipment model topology according to claim 1, is characterized in that: the concrete grammar of device model classification is as follows: first classify by station according to the difference of transformer station; Then in each transformer station, classify again according to electric pressure; Finally carry out again the classification of different models according to the difference of device type, also will classify according to the difference of the equipment mode of connection simultaneously.
3. the wiring diagram automatic generation method based on substation equipment model topology according to claim 1, it is characterized in that: the concrete grammar of device model topological analysis is as follows: be connected in sorted device model according to the topology between device model, adopt the methods analyst of iterative search analysis to there emerged a the wiring relation between device model, take out interval composition simultaneously.
4. the wiring diagram automatic generation method based on substation equipment model topology according to claim 3, it is characterized in that: the concrete grammar that takes out interval composition is: according to the equipment of a partiting template, check in corresponding interval example and whether exist, the template abstracted information that record instance is corresponding.
5. the wiring diagram automatic generation method based on substation equipment model topology according to claim 1, it is characterized in that: the concrete steps that wiring diagram generates are automatically: the autoplacement that first carries out bus and interval, secondly instantiation drafting is carried out in interval, again put other equipment, finally according to wiring relation, equipment is connected to drafting, finally complete the automatic generation of wiring diagram.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510948978.5A CN105608637A (en) | 2015-12-18 | 2015-12-18 | Substation equipment model topology-based wiring diagram automatic generation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510948978.5A CN105608637A (en) | 2015-12-18 | 2015-12-18 | Substation equipment model topology-based wiring diagram automatic generation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105608637A true CN105608637A (en) | 2016-05-25 |
Family
ID=55988555
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510948978.5A Pending CN105608637A (en) | 2015-12-18 | 2015-12-18 | Substation equipment model topology-based wiring diagram automatic generation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105608637A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106371837A (en) * | 2016-08-30 | 2017-02-01 | 国家电网公司 | Automatic construction method and device of configuration interface of alternating current-direct current transformer substation monitoring system |
CN106503298A (en) * | 2016-09-26 | 2017-03-15 | 许继电气股份有限公司 | A kind of Topology connection drawing generating method of intelligent substation and device |
CN106960103A (en) * | 2017-03-30 | 2017-07-18 | 国网福建省电力有限公司 | The automatic generation method and device of a kind of grid graph |
CN107292003A (en) * | 2017-06-06 | 2017-10-24 | 南京南瑞继保电气有限公司 | A kind of automatic generating method of electric network station wiring diagram |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009201177A (en) * | 2008-02-19 | 2009-09-03 | Meidensha Corp | Tap switching controller of transformer in substation |
CN102436523A (en) * | 2011-10-17 | 2012-05-02 | 浙江省电力试验研究院 | Method for automatically mapping digital substation interval wiring diagram |
CN104134175A (en) * | 2014-08-06 | 2014-11-05 | 国网上海市电力公司 | System and method for automatically generating distribution automation master station looped network graph |
CN104392388A (en) * | 2014-11-11 | 2015-03-04 | 国家电网公司 | Automatic imaging method and automatic imaging method for contact diagram of transformer substation of power grid GIS |
-
2015
- 2015-12-18 CN CN201510948978.5A patent/CN105608637A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009201177A (en) * | 2008-02-19 | 2009-09-03 | Meidensha Corp | Tap switching controller of transformer in substation |
CN102436523A (en) * | 2011-10-17 | 2012-05-02 | 浙江省电力试验研究院 | Method for automatically mapping digital substation interval wiring diagram |
CN104134175A (en) * | 2014-08-06 | 2014-11-05 | 国网上海市电力公司 | System and method for automatically generating distribution automation master station looped network graph |
CN104392388A (en) * | 2014-11-11 | 2015-03-04 | 国家电网公司 | Automatic imaging method and automatic imaging method for contact diagram of transformer substation of power grid GIS |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106371837A (en) * | 2016-08-30 | 2017-02-01 | 国家电网公司 | Automatic construction method and device of configuration interface of alternating current-direct current transformer substation monitoring system |
CN106371837B (en) * | 2016-08-30 | 2019-11-01 | 国家电网公司 | Alternating current-direct current monitoring system of electric substation configuration interface automation construction method and device |
CN106503298A (en) * | 2016-09-26 | 2017-03-15 | 许继电气股份有限公司 | A kind of Topology connection drawing generating method of intelligent substation and device |
CN106503298B (en) * | 2016-09-26 | 2019-11-26 | 许继电气股份有限公司 | A kind of Topology connection drawing generating method of intelligent substation and device |
CN106960103A (en) * | 2017-03-30 | 2017-07-18 | 国网福建省电力有限公司 | The automatic generation method and device of a kind of grid graph |
CN106960103B (en) * | 2017-03-30 | 2020-10-13 | 国网福建省电力有限公司 | Automatic generation method and device of power grid graph |
CN107292003A (en) * | 2017-06-06 | 2017-10-24 | 南京南瑞继保电气有限公司 | A kind of automatic generating method of electric network station wiring diagram |
CN107292003B (en) * | 2017-06-06 | 2020-09-04 | 南京南瑞继保电气有限公司 | Automatic generation method of power grid station wiring diagram |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106960103B (en) | Automatic generation method and device of power grid graph | |
CN102801213B (en) | Integrated method and integrated device of SCD (System Configuration Document) of transformer station | |
CN105426300B (en) | Standard conformance test system and method for CIM/E model of power system | |
CN108345739B (en) | Method for identifying CIME and SVG model file information to realize protection fixed value on-line check function and obtain model | |
CN102609520B (en) | Method for exporting model data of substation by filtering | |
CN105608637A (en) | Substation equipment model topology-based wiring diagram automatic generation method | |
CN105809260A (en) | Method for intelligently generating monitoring information point list of dispatching automation system | |
CN108736465A (en) | A kind of future-state electric network model construction method and device | |
CN103544652A (en) | Power grid industry classification load automatic statistical method and system | |
CN103020360A (en) | Integration design method of intelligent substation based on three-dimensional design platform and professional software | |
CN111507001A (en) | Method and system for calculating construction cost of power transformation project, readable storage medium and computer | |
CN105184673A (en) | Power distribution network graph/ model file visualized offline checking method | |
CN102708521A (en) | Mains supply path showing method based on auto-layout of multi-branch tree | |
CN108897913A (en) | A method of plant stand figure is automatically generated by SCD model file | |
CN102169343B (en) | Programmed remote operation system and method of grid centralized monitoring center | |
CN103985022A (en) | Intelligent substation secondary equipment operation and maintenance decision support system and data analysis method | |
CN104077727A (en) | Substation electric equipment machine account intelligent type-in method and system | |
CN104850715A (en) | Urban rail vehicle wiring method based on EPLAN platform | |
CN104156888A (en) | Power system operation risk monitoring method based on comprehensive risk evaluation model | |
CN104112183A (en) | Plug-and-play intelligent scheduling model management system and management method of intelligent substation | |
CN102880988A (en) | Topology comparison-based method and device for importing substation model | |
CN111556108A (en) | Cloud platform-based electric power big data acquisition system and method | |
CN102760194B (en) | Method and system for combining common information models (CIMs) of transformer substations and master scheduling station | |
CN112967376B (en) | Data-driven transformer substation three-dimensional model establishing method and device | |
CN102542028B (en) | Information iterative classification method of smart grid on basis of automatic control theory |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160525 |