CN104794870B - Electric power optical cable maintenance pre-warning system and method - Google Patents

Electric power optical cable maintenance pre-warning system and method Download PDF

Info

Publication number
CN104794870B
CN104794870B CN201510194390.5A CN201510194390A CN104794870B CN 104794870 B CN104794870 B CN 104794870B CN 201510194390 A CN201510194390 A CN 201510194390A CN 104794870 B CN104794870 B CN 104794870B
Authority
CN
China
Prior art keywords
module
early warning
optical cable
electric power
business
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510194390.5A
Other languages
Chinese (zh)
Other versions
CN104794870A (en
Inventor
马超
周洁
孙勇健
刘方舟
曹立斌
田保鹏
杨璐
刘晓晨
张志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Information and Telecommunication Branch of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Information and Telecommunication Branch of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Information and Telecommunication Branch of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510194390.5A priority Critical patent/CN104794870B/en
Publication of CN104794870A publication Critical patent/CN104794870A/en
Application granted granted Critical
Publication of CN104794870B publication Critical patent/CN104794870B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B31/00Predictive alarm systems characterised by extrapolation or other computation using updated historic data

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Computing Systems (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Optical Communication System (AREA)
  • Data Exchanges In Wide-Area Networks (AREA)

Abstract

The invention discloses an electric power optical cable maintenance pre-warning system and method. The system comprises a collecting unit, a data processing unit, a data storage unit, a data storage unit, a service resource module, a controller and a display unit, wherein the collecting unit collects the network configuration resources and performance data in an electric power optical cable transmission network; the data processing unit comprises an optical path information module and a service routing graph module, the optical path information module converts the network configuration resources and performance data transmitted by the collecting unit into optical path information graphs, and the service routing graph module converts the received warning data transmitted by the collecting unit into service routing graphs; the data storage unit comprises an optical cable resource module used for storing electric power communication network optical path information; the service resource module is used for storing service routing information; the controller is used for acquiring and analyzing data in the data storage unit; the display unit is used for displaying pre-warning information and maintenance word order information.

Description

A kind of electric power optical cable maintenance early warning system and its method
Technical field
The present invention relates to a kind of electric power optical cable maintenance early warning system and its method.
Background technology
With the continuous development of power industry, communication speciality and power generation relation also more and more closely, communication service The whether normal safe and stable operation to electrical network play vital effect.Because electrical network scale is increasing, electric power leads to Communication service developing rapidly towards optic communication, the service work of optical cable increasingly affects the operation of electrical network.
General important production business can all have different active and standby two communication ports of route, and two passes are all carried on not On same optical cable.At present Shandong Electric Power Group communication network has the phenomenon that a plurality of optical cable is overhauled simultaneously, if carry same business master, The optical cable of standby passage interrupts maintenance simultaneously, will cause service disconnection, and to electrical network immeasurable loss is brought.At present before maintenance The active and standby multichannel analysis of business are all manually to carry out, and the phenomenon of omission is occurred unavoidably, easily cause the primary channel of important service Interrupt simultaneously.
The content of the invention
To solve the above problems, the invention provides a kind of electric power optical cable maintenance early warning system and its method.
The present invention takes scheme in detail below:
A kind of electric power optical cable overhauls early warning system, including:Collecting unit, the net configuration in its collection electric power optical cable transmission network Resource and performance data;And
Data processing unit, it includes optical path information module and business route module;The optical path information module will connect The net configuration resource and performance data of the collecting unit transmission for receiving generates optical path information figure;The business route module will connect The alarm data of the collecting unit transmission for receiving generates business routing diagram;And
Data storage cell, including cable resource module, it is used to store power telecom network optical path information;And
Service resources module, it is used for storage service routing iinformation;And
Controller, it is used to obtain the power telecom network optical path information and business routing iinformation in data storage cell, with Default power telecom network light path and business routing iinformation under normal circumstances is compared;If controller obtain information with it is normal In the case of any information of power telecom network light path and business routing iinformation when mismatching, controller produces early warning signal, and Maintenance work order information Store is formed to check man's single module;And
Display unit, for showing early warning signal and maintenance work order information.
The power telecom network optical path information, including the length of power telecom network optical cable, type, the operation time limit and core number.
The business routing iinformation for business main road by the operating path with standby route, including node on operating path Information.
The cable resource module and optical path information module set up incidence relation by manual interrelational form.
The service resources module and business route module set up incidence relation by manual interrelational form.
The maintenance work order packet includes repair time, maintenance content, affects optical cable, impact business and arrangement and method for construction.
A kind of method for early warning that early warning system is overhauled based on electric power optical cable, is comprised the following steps:
Step (1):Collecting unit obtains net configuration resource and performance data in electric power optical cable transmission network;
Step (2):Collecting unit believes the data transfer for obtaining to data processing unit, the light path in data processing unit The net configuration resource and performance data that breath module transmits the collecting unit for receiving generates optical path information figure;
The alarm data that business route module in data processing unit transmits the collecting unit for receiving generates industry Business routing diagram;
Step (3):The optical path information figure and business routing diagram that step (2) process is obtained is transmitted and stored to data respectively to be deposited The unit optical cable resource module and service resources module of storage;
Step (4):Controller is obtained and the data in analyze data memory cell, produces early warning signal, and forms maintenance Work order information is stored to check man's single module;
Step (5):Early warning signal and maintenance work order information acquired in step (4) is in display unit.
The detailed process of the step (4) is:
Controller obtains power telecom network optical path information and business routing iinformation in data storage cell, normal with default In the case of power telecom network light path and business routing iinformation be compared;If the information that controller is obtained and electricity under normal circumstances When any information of power communication network light path and business routing iinformation is mismatched, controller produces early warning signal, and forms maintenance Work order information is simultaneously stored into check man's single module.
Beneficial effects of the present invention:
(1) by being analyzed to service operation state and route, unplanned property service disconnection can be effectively prevented, will The safety operation level of electrical network is carried to highest;
(2) danger by overhauling to optical cable carries out system automatic decision, reduces handling time and artificial The erroneous judgement that may cause and careless omission, had both liberated manual labor, and system early warning level is improved again;
(3) by the unplanned interruption of reduction business, operation of power networks level is greatly improved, when reducing grid power blackout Between, the fast development for the whole province's economy provides guarantee.
Description of the drawings
Fig. 1 is the electric power optical cable maintenance early warning system structural representation of the present invention.
Wherein, 1, electric power optical cable transmission network;2nd, collecting unit;3rd, business route module;4th, optical path information module;5th, industry Business resource module;6th, cable resource module;7th, controller;8th, display unit;9th, check man's single module.
Specific embodiment
With reference to the accompanying drawings and detailed description the present invention is further detailed explanation.
As shown in figure 1, a kind of electric power optical cable overhauls early warning system, including:
Collecting unit 2, the net configuration resource and performance data in its collection electric power optical cable transmission network 1;And data processing list Unit, it includes optical path information module 4 and business route module 3;The optical path information module 4 passes the collecting unit for receiving Defeated net configuration resource and performance data generates optical path information figure;The business route module 3 by the collecting unit for receiving The alarm data of transmission generates business routing diagram;And data storage cell, including cable resource module 6, it is used to store electric power Communication network optical path information;And service resources module 5, it is used for storage service routing iinformation;And controller 7, it is used to obtain number According to power telecom network optical path information and business routing iinformation in memory cell, with default power telecom network light under normal circumstances Road and business routing iinformation are compared;If the information that controller 7 is obtained and power telecom network light path and business under normal circumstances When any information of routing iinformation is mismatched, controller 7 produces early warning signal, and forms maintenance work order information Store to check man Single module 9;
Wherein, the length of the power telecom network optical path information, including power telecom network optical cable, type, the operation time limit and Core number;The business routing iinformation for business main road by the operating path with standby route, including on operating path node letter Breath, wherein, the information of each node is corresponding with optical cable core;And
Display unit 8, for showing early warning signal and maintenance work order information.
The cable resource module 6 and optical path information module 4 set up incidence relation by manual interrelational form.
The service resources module 5 and business route module 3 set up incidence relation by manual interrelational form.
The maintenance work order packet includes repair time, maintenance content, affects optical cable, impact business and arrangement and method for construction.
A kind of method for early warning that early warning system is overhauled based on electric power optical cable, is comprised the following steps:
Step (1):Collecting unit 2 obtains net configuration resource and performance data in electric power optical cable transmission network 1;
Step (2):Collecting unit 2 is by the data transfer for obtaining to data processing unit, the light path in data processing unit The net configuration resource and performance data that information module 4 transmits the collecting unit 2 for receiving generates optical path information figure;
The alarm data that business route module 3 in data processing unit transmits the collecting unit 2 for receiving is generated Business routing diagram;
Step (3):The optical path information figure and business routing diagram that step (2) process is obtained is transmitted and stored to data respectively to be deposited The unit optical cable resource module 6 of storage and service resources module 5;
Step (4):Controller 7 is obtained and the data in analyze data memory cell, produces early warning signal, and forms maintenance Work order information is stored to check man's single module 9, and its detailed process is:
Controller 7 obtains power telecom network optical path information and business routing iinformation in data storage cell, with it is default just Power telecom network light path and business routing iinformation in the case of often is compared;If controller obtain information with normal circumstances When any information of power telecom network light path and business routing iinformation is mismatched, controller 7 produces early warning signal, and forms inspection Repair work order information and store into check man's single module 9;
Step (5):Early warning signal and maintenance work order information acquired in step (4) is in display unit 8.
Although the above combines accompanying drawing and the specific embodiment process of the present invention is described, but is not to this The restriction of invention protection domain, one of ordinary skill in the art understand, on the basis of technical solution of the present invention, those skilled in the art Various modifications that creative work just can make or deformation can not be paid still within protection scope of the present invention.

Claims (10)

1. a kind of electric power optical cable overhauls early warning system, it is characterised in that collecting unit, the net in its collection electric power optical cable transmission network Configuration resource and performance data;And
Data processing unit, it includes optical path information module and business route module;The optical path information module will be received Collecting unit transmission net configuration resource and performance data generate optical path information figure;The business route module will be received Collecting unit transmission alarm data generate business routing diagram;And
Data storage cell, including cable resource module, it is used to store power telecom network optical path information;And
Service resources module, it is used for storage service routing iinformation;And
Controller, it is used to obtain the power telecom network optical path information and business routing iinformation in data storage cell, and default Power telecom network light path and business routing iinformation under normal circumstances is compared;If information and normal condition that controller is obtained When any information of lower power telecom network light path and business routing iinformation is mismatched, controller produces early warning signal, and is formed Maintenance work order information Store is to check man's single module;And
Display unit, for showing early warning signal and maintenance work order information.
2. a kind of electric power optical cable as claimed in claim 1 overhauls early warning system, it is characterised in that the power telecom network light path Information, including the length of power telecom network optical cable, type, the operation time limit and core number.
3. a kind of electric power optical cable as claimed in claim 1 overhauls early warning system, it is characterised in that the business routing iinformation is The main road of business by the operating path with standby route, including on operating path node information.
4. a kind of electric power optical cable as claimed in claim 1 overhauls early warning system, it is characterised in that the cable resource module and Optical path information module sets up incidence relation by manual interrelational form.
5. a kind of electric power optical cable as claimed in claim 1 overhauls early warning system, it is characterised in that the service resources module and Business route module and sets up incidence relation by manual interrelational form.
6. a kind of electric power optical cable as claimed in claim 1 overhauls early warning system, it is characterised in that the maintenance work order packet Include repair time, maintenance content, affect optical cable, impact business and arrangement and method for construction.
7. a kind of electric power optical cable based on as described in claim 1-6 any claim overhauls the method for early warning of early warning system, Characterized in that, comprising the following steps:
Step (1):Collecting unit obtains net configuration resource and performance data in electric power optical cable transmission network;
Step (2):Collecting unit is by the data transfer for obtaining to data processing unit, the optical path information mould in data processing unit The net configuration resource and performance data that block transmits the collecting unit for receiving generates optical path information figure;
The alarm data that business route module in data processing unit transmits the collecting unit for receiving generates business road By scheming;
Step (3):The optical path information figure and business routing diagram that step (2) process is obtained is transmitted and stored respectively to data storage Unit optical cable resource module and service resources module;
Step (4):Controller is obtained and the data in analyze data memory cell, produces early warning signal, and forms maintenance work order Information Store is to check man's single module;
Step (5):Early warning signal and maintenance work order information acquired in step (4) is in display unit.
8. a kind of electric power optical cable as claimed in claim 7 overhauls the method for early warning of early warning system, it is characterised in that the step (4) detailed process is:
Controller obtains power telecom network optical path information and business routing iinformation in data storage cell, with default normal condition Under power telecom network light path and business routing iinformation be compared;If the information that controller is obtained is led to electric power under normal circumstances When any information of letter net light path and business routing iinformation is mismatched, controller produces early warning signal, and forms maintenance work order Information is simultaneously stored into check man's single module.
9. a kind of electric power optical cable as claimed in claim 7 overhauls the method for early warning of early warning system, it is characterised in that the optical cable Resource module and optical path information module set up incidence relation by manual interrelational form.
10. a kind of electric power optical cable as claimed in claim 7 overhauls the method for early warning of early warning system, it is characterised in that the industry Business resource module and business route module set up incidence relation by manual interrelational form.
CN201510194390.5A 2015-04-22 2015-04-22 Electric power optical cable maintenance pre-warning system and method Active CN104794870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510194390.5A CN104794870B (en) 2015-04-22 2015-04-22 Electric power optical cable maintenance pre-warning system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510194390.5A CN104794870B (en) 2015-04-22 2015-04-22 Electric power optical cable maintenance pre-warning system and method

Publications (2)

Publication Number Publication Date
CN104794870A CN104794870A (en) 2015-07-22
CN104794870B true CN104794870B (en) 2017-05-03

Family

ID=53559641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510194390.5A Active CN104794870B (en) 2015-04-22 2015-04-22 Electric power optical cable maintenance pre-warning system and method

Country Status (1)

Country Link
CN (1) CN104794870B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106357530B (en) * 2016-10-12 2019-08-16 广西电网有限责任公司 Route detecting method and device under a kind of N-1 maintenance model
CN106357531B (en) * 2016-10-12 2019-08-16 广西电网有限责任公司 Route detecting method and device under a kind of N-X maintenance model
CN108988938A (en) * 2018-07-22 2018-12-11 国网山东省电力公司信息通信公司 Electric power communication network optical cable risk early warning and disposal method
CN109187670A (en) * 2018-10-16 2019-01-11 国网山东省电力公司信息通信公司 A kind of communications optical cable splice tray intelligent checking system
CN110705232B (en) * 2019-08-27 2023-04-07 国网山东省电力公司信息通信公司 Method and system for generating service state analysis report of power communication network maintenance influence
CN112614314B (en) * 2020-12-03 2022-08-26 广东电力通信科技有限公司 Power transmission network service configuration method and system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102064883B (en) * 2010-08-27 2013-03-27 天津大学 Operational decision making system of lumped control multi-type heterogeneous electricity communication network
CN102437922B (en) * 2011-09-24 2016-01-20 国网电力科学研究院 A kind of power telecom network business impact analysis method based on N-1 principle
US9000374B2 (en) * 2012-06-08 2015-04-07 Ut-Battelle, Llc EGR distribution and fluctuation probe based on CO2 measurements
CN103310387B (en) * 2013-05-20 2016-08-03 国家电网公司 A kind of power telecom network method of operation Security Checking method
CN104038371B (en) * 2014-05-22 2018-05-01 国家电网公司 A kind of electric power communication transmission network adaptive performance acquisition method

Also Published As

Publication number Publication date
CN104794870A (en) 2015-07-22

Similar Documents

Publication Publication Date Title
CN104794870B (en) Electric power optical cable maintenance pre-warning system and method
CN102437922B (en) A kind of power telecom network business impact analysis method based on N-1 principle
CN102710443B (en) A kind of power communication relaying protection business impact analysis method and system thereof
CN102801732A (en) Power communication backbone network safety risk assessment method based on network topology
CN105591691A (en) GIS-based communication optical cable online monitoring system and GIS-based communication optical cable fault point positioning method
CN106452571B (en) Electric power terminal communication access net topological relation faulty section determines and analysis method
CN110493670B (en) Optical cable interruption judgment method and device
CN105591770A (en) Determination method and apparatus for fault type in PON
CN109672493B (en) Method and apparatus for determining wavelength division device path
CN107231188B (en) Method for rapidly identifying optical fiber link breaking point of intelligent station
CN106788701B (en) A kind of method and system positioning the segment fault of ODN network
CN110601751A (en) Power grid communication optical cable interruption monitoring method and device
CN114244737A (en) Method, device and system for evaluating network quality
CN206506531U (en) Intelligent optical cable fusion connecting disk and the optical signal detecting module for optical cable fusion connecting disk
CN108768530A (en) A kind of data transfer control system and its method of fiber optical transceiver
CN109995428A (en) The optical path detection method and device of passive optical network
CN204408345U (en) Optical cable on-line monitoring system
CN105306135B (en) Link polling detection method and device
CN107147518A (en) Power communication overhauls the automatic risk analysis model of influence business and its analysis method
CN202615008U (en) Optical fiber distribution frame capable of automatically monitoring transmission quality of optical fibers
CN208723623U (en) A kind of photovoltaic power station monitoring system
CN201296796Y (en) Control system of Ethernet network aluminum cell cell-control machine
CN118264316B (en) Digital monitoring and data analysis method for optical fiber link
CN104333413A (en) Optical cable online monitoring system
CN205015531U (en) Intelligence optic fibre distribution device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant