CN104695497A - Earthmoving machine construction technology for large earth and rock engineering - Google Patents

Earthmoving machine construction technology for large earth and rock engineering Download PDF

Info

Publication number
CN104695497A
CN104695497A CN201410839417.7A CN201410839417A CN104695497A CN 104695497 A CN104695497 A CN 104695497A CN 201410839417 A CN201410839417 A CN 201410839417A CN 104695497 A CN104695497 A CN 104695497A
Authority
CN
China
Prior art keywords
construction
native machine
peel ply
layer
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410839417.7A
Other languages
Chinese (zh)
Other versions
CN104695497B (en
Inventor
沈旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Sanhe Green Energy Environment Co ltd
Original Assignee
WUXI SANHE HEAVY MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUXI SANHE HEAVY MACHINERY CO Ltd filed Critical WUXI SANHE HEAVY MACHINERY CO Ltd
Priority to CN201410839417.7A priority Critical patent/CN104695497B/en
Publication of CN104695497A publication Critical patent/CN104695497A/en
Application granted granted Critical
Publication of CN104695497B publication Critical patent/CN104695497B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses an earthmoving machine construction technology for a large earth and rock engineering. According to the construction depth and the excavation depth each time, a construction area can be divided into N layers, and each layer is stripped through circular and orderly construction. The earthmoving machine construction technology comprises steps as follows: step one, an unloading hopper is arranged on the ground where the construction elevation of a first layer of the construction area is located, excavation equipment is arranged on the excavation surface, earthmoving machines and mobile belt conveyors are connected to the rear part, the number of the mobile belt conveyors is gradually increased according to the excavation speed of the excavation equipment until the maximum working length of each earthmoving machine is reached; step two, the excavation equipment and the earthmoving machines return to a starting point, the construction of a second stripping layer is started, when the second stripping layer is stripped to the length at which the mobile belt conveyors is required to be increased, the mobile belt conveyors paved on the first stripping layer are moved to the second stripping layer according to the excavation speed of the excavation equipment, and each layer is constructed circularly and orderly. Therefore, the construction machinery of the former layer is sufficiently utilized, the quantity of the machinery is small, a few construction workers are required, the management is easy, and the construction accident rate is further greatly reduced.

Description

The upper native machine construction technology of large-scale earth and rock works
Technical field
The present invention relates to engineering field, be specifically related to the upper native machine construction technology of large-scale earth and rock works.
Background technology
If upper native owner is mechanical for a large-scale construction works of large-scale earth and rock works and opencut engineering design research and development.This equipment is broken, conveying function, the major works of, service year limit for length large for construction party amount.Upper native facility have that production capacity is large, efficiency is high, adapt to that complex working condition carries out constructing, transport gradient is large, simple to operate, easy to maintenance, realize the advantages such as modern management, for completing major works, guaranteeing that the construction period accomplishes strong guarantee.
Having under favourable construction equipment condition, for completing major works, upper native machine must have a set of rational construction technology, ability reasonable arrangement, orderly construction.Because the construction breadth of major works is vast, traditional construction method is difficult to carry out system layout, traditional construction machinery as excavator and transport vehicle with the use of, but its construction ability is lower, construction machinery enormous amount, construction worker is many, and it is more difficult to manage, construction accident incidence also improves greatly, is unfavorable for normally carrying out of construction.
Summary of the invention
The present invention mainly provide a kind of can according to the length of the size of engineering quantity, construction period, the quantity of native machine on reasonable disposition, and basic realization controls automatically, construction does not stop to break continuously, and operating personnel are few, the upper native machine construction technology of failure rate is low.
The technical solution adopted for the present invention to solve the technical problems is: the upper native machine construction technology of large-scale earth and rock works, comprises the steps:
A. the first peel ply construction
According to the construction depth of the construction area of every native machine in the sky, determine the degree of depth that each cubic metre of earth and stone is peeled off; Ground residing for the Construction Elevation of works area is arranged discharging hopper, and excavation surface arranges excavating equipment, and rear connects native machine and portable belt conveyer, and portable belt conveyer is connected with ground discharging hopper; According to the driving speed of excavating equipment, progressively increase the quantity of portable belt conveyer, reach the maximum functional length of native machine; By translation and the driving of excavating equipment, whole first peel ply construction is peeled off and terminates;
B. peel ply circulation construction
After the first peel ply has been constructed, starting point got back to by excavating equipment and upper native machine, enter the second peel ply in the same way, when being stripped to the length needing to increase mobile belt machine, the mobile belt machine laid by former first peel ply moves to the second peel ply by the driving speed of excavating equipment, carries out the orderly construction that circulates;
According to construction depth, according to the degree of depth of digging under each, works area can be divided at least two-layer, every layer is dug down successively, for ensureing that equipment has walking passageway, starting point cross section often increases a portable belt conveyer, just many equipment walking passageway, and the final stepped profile that formed is to construction completion elevation.
As the further improvement of the upper native machine construction technology of the large-scale earth and rock works of the present invention, according to construction area, according to the duration, the quantity of described native machine is one or more, constructs separately or multiple stage, native machine coordinates and constructs in construction area from two or four direction from a direction in construction area; Along with digging dark constantly carrying out, final formation is with stair-stepping deep foundation ditch, different construction breadths, the foundation ditch form that final formation is different.
As the further improvement of the upper native machine construction technology of the large-scale earth and rock works of the present invention, upper native machine is peeling off the cubic metre of earth and stone or the mineral of each peel ply, all be delivered in ground transfer hopper by portable belt conveyer, carry out rejecting to spoil ground or mining site with dumping engineering truck, or be directly delivered to material maximal end point by belt conveyor.
Beneficial effect of the present invention: scientifically according to the size of engineering quantity, the length of construction period, the quantity of native machine on reasonable disposition, the a set of equipment related in this construction technology realizes automatic control substantially, construction does not stop to break continuously, systematicness is strong, and operating personnel are few, and management is easy, failure rate is low, effectively can ensure construction speed, control the construction period.
Accompanying drawing explanation
Fig. 1 is that first floor original state schematic diagram is peeled off in the upper native machine construction technology construction of the large-scale earth and rock works of the present invention;
Fig. 2 is the schematic diagram of the supreme native machine maximum functional length of upper native machine construction technology stripping first floor of the large-scale earth and rock works of the present invention;
Fig. 3 is the schematic diagram of the supreme native machine maximum functional length of the upper native machine construction technology stripping second layer of the large-scale earth and rock works of the present invention;
Fig. 4 is the schematic diagram forming notch cuttype cross section after the upper native machine construction technology of the large-scale earth and rock works of the present invention peels off multilayer;
Fig. 5 be the large-scale earth and rock works of the present invention upper native machine construction technology two platform on the schematic diagram of native machine coordinative construction;
Fig. 6 is the transfer schematic diagram of the material separated in the upper native machine construction technology of the large-scale earth and rock works of the present invention;
Fig. 7 is the enlarged diagram of Fig. 6 medium cloud line part;
Fig. 8 is the material transfer schematic diagram of another kind of form of construction work;
Fig. 9 is Fig. 8 medium cloud line part enlarged diagram 1.;
Figure 10 is Fig. 8 medium cloud line part enlarged diagram 2.;
Figure 11 is the material transfer schematic diagram of another form of construction work;
Figure 12 is the enlarged diagram of Figure 11 medium cloud line part;
Figure 13 is the material transfer schematic diagram of another kind of form of construction work;
Figure 14 is the enlarged diagram of encircled portion in Figure 13;
Figure 15 is the material transfer schematic diagram of another kind of form of construction work;
Figure 16 is the enlarged diagram of Figure 15 medium cloud line part;
Figure 17 is the enlarged diagram of discharging hopper in Fig. 1 to Fig. 5;
Figure 18 is the enlarged diagram of portable belt conveyer in Fig. 1 to Fig. 5;
Figure 19 is the enlarged diagram of upper native machine in Fig. 1 to Fig. 3;
Figure 20 is the enlarged diagram of excavating equipment in Fig. 1 to Fig. 5.
In figure: 1, discharging hopper 2, excavating equipment 3, upper native machine 4, portable belt conveyer 5, overfall.
Detailed description of the invention
Clearly understanding to have technical characteristic of the present invention, object and effect, now contrasting accompanying drawing and describing the specific embodiment of the present invention in detail.
The upper native machine construction technology of large-scale earth and rock works, first according to working drawing and geologic report, to the character of engineering, content, technical requirements, surrounding enviroment, geological condition etc. are done conscientiously, fully to study, for equipment is marched into the arena the work of preparing.
Secondly, according to size and duration, particularly construction area and the degree of depth of engineering quantity, reasonable selection carried out to machine native on construction equipment and determines the quantity of construction machinery, arranging, providing seat in the plane coordinate point.
Processing step is as follows:
According to the construction depth of the construction area of every native machine in the sky, determine the degree of depth that each cubic metre of earth and stone is peeled off, as shown in Figure 1, dummy work area Construction Elevation is ± 0, and dig the degree of depth 4 meters under each, the first peel ply length is stripped to the maximum length of native machine.± 0 ground is arranged discharging hopper 1, excavation surface arranges excavating equipment 2, and rear connects native machine 3 and portable belt conveyer 4, and portable belt conveyer 4 is connected with ground discharging hopper 1.According to the driving speed of excavating equipment, progressively increase the quantity of portable belt conveyer, reach the maximum functional length of native machine, as Fig. 2.By translation and the driving of excavating equipment, whole first peel ply construction is peeled off and terminates.
After the first peel ply has been constructed, starting point got back to by excavating equipment and upper native machine, enter the second peel ply in the same way, when being stripped to the length needing to increase mobile belt machine, the mobile belt machine laid by former first peel ply moves to the second peel ply by the driving speed of excavating equipment, carry out the orderly construction that circulates, as Fig. 3, in work progress, overfall 5 auxiliary construction can be increased according to actual needs.
According to construction depth, according to the degree of depth of digging under each, works area can be divided into N layer, every layer is dug down successively, for ensureing that equipment has walking passageway, starting point cross section often increases a portable belt conveyer, just many equipment walking passageway, final formation stepped profile is construction completion elevation extremely, as shown in Figure 4.
According to construction area, according to the duration, can be that on a platform, native machine is constructed separately, also can native machine coordinative construction in multiple stage, as shown in Figure 5, along with digging dark constantly carrying out, the stair-stepping deep foundation ditch of final formation band, different construction breadths, the foundation ditch form that final formation is different.
Upper native machine, peeling off the cubic metre of earth and stone or the mineral of each peel ply, is all delivered in ground transfer hopper by portable belt conveyer.Available dumping engineering truck carries out rejecting to spoil ground or mining site, also directly can be delivered to material maximal end point by belt conveyor, and this according to haul distance, can select rationally economic means of transportation, as shown in Figure 6.
This construction technology construction ability is strong, and construction machinery quantity is few, and construction worker is few, and easily, construction accident incidence is also low, is beneficial to normally carrying out of construction, effectively can ensures construction speed in management, controls the construction period.
Above content is in conjunction with concrete optimal technical scheme further description made for the present invention, can not assert that specific embodiment of the invention is confined to these explanations.For general technical staff of the technical field of the invention, without departing from the inventive concept of the premise, some simple deduction or replace can also be made, all should be considered as belonging to protection scope of the present invention.

Claims (3)

1. the upper native machine construction technology of large-scale earth and rock works, is characterized in that, comprise the steps:
A. the first peel ply construction
According to the construction depth of the construction area of every native machine in the sky, determine the degree of depth that each cubic metre of earth and stone is peeled off; Ground residing for the Construction Elevation of works area is arranged discharging hopper, and excavation surface arranges excavating equipment, and rear connects native machine and portable belt conveyer, and portable belt conveyer is connected with ground discharging hopper; According to the driving speed of excavating equipment, progressively increase the quantity of portable belt conveyer, reach the maximum functional length of native machine; By translation and the driving of excavating equipment, whole first peel ply construction is peeled off and terminates;
B. peel ply circulation construction
After the first peel ply has been constructed, starting point got back to by excavating equipment and upper native machine, enter the second peel ply in the same way, when being stripped to the length needing to increase mobile belt machine, the mobile belt machine laid by former first peel ply moves to the second peel ply by the driving speed of excavating equipment, carries out the orderly construction that circulates;
According to construction depth, according to the degree of depth of digging under each, works area can be divided at least two-layer, every layer is dug down successively, for ensureing that equipment has walking passageway, starting point cross section often increases a portable belt conveyer, just many equipment walking passageway, and the final stepped profile that formed is to construction completion elevation.
2. the upper native machine construction technology of large-scale earth and rock works according to claim 1, it is characterized in that, according to construction area, according to the duration, the quantity of described native machine is one or more, constructs separately or multiple stage, native machine coordinates and constructs in construction area from two or four direction from a direction in construction area; Along with digging dark constantly carrying out, final formation is with stair-stepping deep foundation ditch, different construction breadths, the foundation ditch form that final formation is different.
3. the upper native machine construction technology of large-scale earth and rock works according to claim 1, it is characterized in that, described native machine is peeling off the cubic metre of earth and stone or the mineral of each peel ply, all be delivered in ground transfer hopper by portable belt conveyer, carry out rejecting to spoil ground or mining site with dumping engineering truck, or be directly delivered to material maximal end point by belt conveyor.
CN201410839417.7A 2014-12-30 2014-12-30 The upper native machine construction technology of large-scale earth and rock works Active CN104695497B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410839417.7A CN104695497B (en) 2014-12-30 2014-12-30 The upper native machine construction technology of large-scale earth and rock works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410839417.7A CN104695497B (en) 2014-12-30 2014-12-30 The upper native machine construction technology of large-scale earth and rock works

Publications (2)

Publication Number Publication Date
CN104695497A true CN104695497A (en) 2015-06-10
CN104695497B CN104695497B (en) 2019-11-22

Family

ID=53343010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410839417.7A Active CN104695497B (en) 2014-12-30 2014-12-30 The upper native machine construction technology of large-scale earth and rock works

Country Status (1)

Country Link
CN (1) CN104695497B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105173673A (en) * 2015-10-13 2015-12-23 云南省小龙潭矿务局机修总厂 Soil dumping process for multi-directional transferring and machine head dead zone eliminating by waste soil field rubber belt machines
CN106608491A (en) * 2015-10-22 2017-05-03 中铁二局集团有限公司 Adjustable conveying belt muck discharging method for high-slope-ratio entrance and exit channel
CN109319522A (en) * 2018-08-31 2019-02-12 中国华冶科工集团有限公司 A kind of pit earthwork transport device
CN111549846A (en) * 2020-04-30 2020-08-18 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing treatment
CN114229523A (en) * 2021-12-24 2022-03-25 焦作科瑞森重装股份有限公司 Mining and stripping process and matched equipment for mine raw materials for mechanized production
CN115341602A (en) * 2022-08-30 2022-11-15 徐少钢 Flexible control soil feeding excavation system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5655614A (en) * 1979-10-09 1981-05-16 Hiroshi Tsuji Ground construction work
CN1814918A (en) * 2006-03-02 2006-08-09 顾建华 Earthwork construction method
CN201269103Y (en) * 2008-08-20 2009-07-08 三一重型装备有限公司 Drift driving construction system
CN101775821A (en) * 2009-12-10 2010-07-14 中国建筑一局(集团)有限公司 Device and method for vertically transporting earthwork through reverse construction method
CN103410152A (en) * 2013-09-05 2013-11-27 中交公路养护工程技术有限公司 Construction method for long, narrow and deep foundation pit soil excavation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5655614A (en) * 1979-10-09 1981-05-16 Hiroshi Tsuji Ground construction work
CN1814918A (en) * 2006-03-02 2006-08-09 顾建华 Earthwork construction method
CN201269103Y (en) * 2008-08-20 2009-07-08 三一重型装备有限公司 Drift driving construction system
CN101775821A (en) * 2009-12-10 2010-07-14 中国建筑一局(集团)有限公司 Device and method for vertically transporting earthwork through reverse construction method
CN103410152A (en) * 2013-09-05 2013-11-27 中交公路养护工程技术有限公司 Construction method for long, narrow and deep foundation pit soil excavation

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105173673A (en) * 2015-10-13 2015-12-23 云南省小龙潭矿务局机修总厂 Soil dumping process for multi-directional transferring and machine head dead zone eliminating by waste soil field rubber belt machines
CN106608491A (en) * 2015-10-22 2017-05-03 中铁二局集团有限公司 Adjustable conveying belt muck discharging method for high-slope-ratio entrance and exit channel
CN109319522A (en) * 2018-08-31 2019-02-12 中国华冶科工集团有限公司 A kind of pit earthwork transport device
CN111549846A (en) * 2020-04-30 2020-08-18 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing treatment
CN111549846B (en) * 2020-04-30 2021-09-24 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing treatment
CN114229523A (en) * 2021-12-24 2022-03-25 焦作科瑞森重装股份有限公司 Mining and stripping process and matched equipment for mine raw materials for mechanized production
CN114229523B (en) * 2021-12-24 2023-08-29 焦作科瑞森重装股份有限公司 Mining and stripping process for mine raw materials for mechanized production and matched equipment
CN115341602A (en) * 2022-08-30 2022-11-15 徐少钢 Flexible control soil feeding excavation system

Also Published As

Publication number Publication date
CN104695497B (en) 2019-11-22

Similar Documents

Publication Publication Date Title
CN104695497A (en) Earthmoving machine construction technology for large earth and rock engineering
CN103470262A (en) Mining method of nearly horizontal mineral deposit of opencast coal field by casting and internally dumping
CA2883015C (en) A system for the reduction in applied energy, improved efficiencies and reduced costs in open pit mining
CN104806248B (en) Slice mining method for small-scale opencast quarry
CN103216238A (en) Open pit coal mine mining process
CN101899976A (en) Continuous coal mining process method of open-pit coal mine
CN107201901B (en) Short distance high gas layer group's thin coal seam unmanned working face mining device and method
CN106988746A (en) A kind of outdoor mining methods that become more meticulous of slight slope and thin ore body
CN104790956A (en) Remote control heading machine tunnel type or fully-mechanized top coal exploitation end slope coal technology
CN102889084A (en) Continuous mining technique for thin coal layer of opencast coal mine
CN102278115A (en) High-efficiency safe environment-friendly mining method for rare shallow-buried ore layer in irregular strip-shaped distribution
CN102493813A (en) Shield tunneling machine for underground pipeline
CN104358574B (en) The horizontal room-and-pillar stoping of gently inclined orebody
CN101892843A (en) Porous bottom-dump conveyer of solid-state filling material
CN102758442A (en) Earth excavation method and open-cut tunnel construction method
CN103388478B (en) Forming method for transportation road of bucket shovel applied to open pit coal mine
AU2015100066A4 (en) A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining
CN104088641B (en) Longwell descending slicing spoil vacation top coal-mining method
CN108547658B (en) A kind of high inclination-angle ultra-thin coal seam spoil is from slipping backfilling goaf method
CN105155547A (en) Construction method for deep foundation pit excavation on steep slope terrain
JP2017048588A (en) Excavated object carrying-out system and carrying-out method
CN105626068B (en) Help the method for dismounting of bridge in open coal mine end
CN202731927U (en) Tunnel construction device
CA1145367A (en) Underspoil slurry haulage
CN203729998U (en) Integrated rock drift tunneling production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220905

Address after: No. 28, Heguqiao, Huaxin Community, Huazhuang Street, Binhu District, Wuxi City, Jiangsu Province, 214000

Patentee after: Ma Sheng

Patentee after: Shen Xu

Address before: Block B22-23, Shuofang Industrial Concentration Zone, New District, Wuxi City, Jiangsu Province, 214000

Patentee before: WUXI SANHE HEAVY MACHINERY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220919

Address after: 214000 room 508, floor 5, No. 6, Xingguang commercial center, Xinwu District, Wuxi City, Jiangsu Province

Patentee after: Wuxi Sanhe green energy environment Co.,Ltd.

Address before: No. 28, Heguqiao, Huaxin Community, Huazhuang Street, Binhu District, Wuxi City, Jiangsu Province, 214000

Patentee before: Ma Sheng

Patentee before: Shen Xu