Adibi, 2000 - Google Patents
Power system restoration: methodologies & implementation strategiesAdibi, 2000
View PDF- Document ID
- 2057002513407052806
- Author
- Adibi M
- Publication year
External Links
Snippet
" At a time when bulk power systems operate close to their design limits, the restructuring of the electric power industry has created vulnerability to potential blackouts. Prompt and effective power system restoration is essential for the minimization of downtime and costs to …
- 238000000034 method 0 title abstract description 25
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/008—Circuit arrangements for ac mains or ac distribution networks involving trading of energy or energy transmission rights
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Adibi | Power system restoration: methodologies & implementation strategies | |
Adibi et al. | Power system restoration planning | |
Sobajic et al. | An artificial intelligence system for power system contingency screening | |
Mariani et al. | Control of modern integrated power systems | |
Allan et al. | Probabilistic methods applied to electric power systems—Are they worth it? | |
Germond et al. | Survey of knowledge-based systems in power systems: Europe | |
Billinton et al. | Generalized n+ 2 state system Markov model for station-oriented reliability evaluation | |
Brown | Contingencies evaluated by a Z-matrix method | |
Nobile | Power system studies for cogeneration: What's really needed? | |
Schainker et al. | On-line dynamic stability analysis using distributed computing | |
Enesi et al. | Reliability modeling and analysis of high voltage power equipment: a case study of Ajaokuta Steel Company Limited (ASCL) | |
Magg | Procurement and Functional Specification of HVDC Systems | |
Mnukwa | Upgrading existing power supply at the Port of Durban. | |
Endrejat et al. | Electrical best practices and lessons learned from a chemical megaproject | |
TSEGA | CRITICAL CLEARING TIME EVALUATION OF ETHIOPIAN 230 KV/400 KV POWER SYSTEM | |
Zare Oskouei et al. | Electrical Challenges Associated with Integrating Renewable Energy Sources into Power Grids | |
Ault et al. | Specification and testing of a comprehensive strategic analysis framework for distributed generation | |
Billinton et al. | A hybrid deterministic/probabilistic technique for HVDC system reliability evaluation | |
Storage et al. | A National Battery Energy Storage Test | |
BEWKET | CONTINGENCY ANALYSIS OF ETHIOPIAN POWER SYSTEM ON 230 kV AND 400 kV TRANSMISSION LINES | |
Trefny et al. | Integration of an operations information system into an energy management and control system | |
KELEMEWORK | TRANSMISSION LINE CONTINGENCY ANALYSIS (A Case Study in North-West Region of Ethiopian Electric Power Network) | |
Rigler | Reliability of Distribution Systems | |
Drewiske et al. | What Do You Do When the Lights Go Out?: Constructing a Procedure for Unplanned Power Failure | |
Jansen et al. | Reliability Evaluation Pirogram for the Design of Auxiliary Electrical Systems and Distribution Substations |