US20140369750A1 - Grout containment sheet and method - Google Patents
Grout containment sheet and method Download PDFInfo
- Publication number
- US20140369750A1 US20140369750A1 US13/917,941 US201313917941A US2014369750A1 US 20140369750 A1 US20140369750 A1 US 20140369750A1 US 201313917941 A US201313917941 A US 201313917941A US 2014369750 A1 US2014369750 A1 US 2014369750A1
- Authority
- US
- United States
- Prior art keywords
- grout
- excavation
- panel
- sheet
- moisture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/003—Pavings made of prefabricated single units characterised by material or composition used for beds or joints; characterised by the way of laying
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
- E01C23/03—Arrangements for curing paving; Devices for applying curing means; Devices for laying prefabricated underlay, e.g. sheets, membranes; Protecting paving under construction or while curing, e.g. use of tents
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
- E01C23/06—Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
- E01C23/10—Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for raising or levelling sunken paving; for filling voids under paving; for introducing material into substructure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/001—Pavings made of prefabricated single units on prefabricated supporting structures or prefabricated foundation elements except coverings made of layers of similar elements
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/06—Pavings made of prefabricated single units made of units with cement or like binders
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/005—Individual couplings or spacer elements for joining the prefabricated units
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C7/00—Coherent pavings made in situ
- E01C7/08—Coherent pavings made in situ made of road-metal and binders
- E01C7/10—Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
- E01C7/14—Concrete paving
- E01C7/147—Repairing concrete pavings, e.g. joining cracked road sections by dowels, applying a new concrete covering
Definitions
- This invention relates to a moisture (i.e., water) impermeable grout containment sheet and to a method including the step of locating the sheet within an excavation so as to lie between a (e.g., concrete) panel that has been lowered into the excavation and grout that has been pumped below the panel.
- the group containment sheet and method have particular application during roadway construction or repair where a plurality of concrete panels are laid in excavations formed in a road bed and connected to one another to support vehicular traffic.
- a common technique for building such roadways is to lay a number of heavy concrete panels or slabs end-to-end and side-by-side one another. All of the panels must be held in place relative to one another and connected together to establish a smooth and continuous driving surface. The foregoing is often accomplished by first grading a road bed and cutting excavations therein within which the concrete panels are laid.
- a grout containment sheet and method having particular application, for example, during roadway construction or repair when excavations are cut into a road bed and (e.g., precast concrete) panels are laid inside the excavations to be connected end-to-end and/or side-by-side.
- a moisture (i.e., water) impermeable (e.g., polyurethane) grout containment sheet Prior to laying a panel within an excavation, a moisture (i.e., water) impermeable (e.g., polyurethane) grout containment sheet is positioned inside the excavation to cover at least the bottom thereof.
- the grout containment, sheet must be sufficiently strong to prevent water from passing therethrough.
- the panel is lowered into the excavation so as to lie upon the grout containment sheet.
- grout or a similar adhesive bonding material is pumped below the panel such as, for example, by way of filler tubes which run through the panel.
- the grout containment sheet lies between the grout and the road bed above which the panel is located.
- the grout containment sheet establishes a containment envelope around the grout throughout the construction project to prevent the grout from migrating away from the panel.
- the grout containment sheet creates a barrier that prevents the grout from both drying out as a consequence of the moisture of the grout being absorbed by the road bed and from becoming too wet as a consequence of being exposed to rain water and ground water. Accordingly, the maximum strength, structural integrity and load-bearing characteristics of the grout upon which the panel is laid and supported can be maintained.
- FIG. 1 shows an excavation that has been cut into a road bed and a grout containment sheet located within and covering the bottom of the excavation according to a preferred embodiment of this invention
- FIG. 2 shows a solid panel such as, for example, a precast concrete panel used during the construction of a roadway lowered into the excavation and laying upon the grout containment sheet;
- FIG. 3 shows an adhesive bonding material (e.g., grout) pumped into the excavation below the panel, such that the grout containment sheet creates a water impermeable containment barrier between the grout and the road bed.
- adhesive bonding material e.g., grout
- the grout containment sheet and method herein disclosed have particular application during roadway construction and/or repair where a plurality of concrete panels are laid inside one or more excavations so as to be connected end-to-end and/or side-by-side one another.
- the system and method are also advantageous to facilitating the removal of a panel from its excavation should such removal be required during subsequent roadway maintenance and repair.
- FIG. 1 shows a single excavation 10 that has been cut into a road bed 15 .
- the excavation 10 can be cut by means of any of a variety of available construction machinery and plays no role in the present invention. In the event a roadway is being constructed, either a single continuous excavation or a series of adjacent excavations will be cut into the road bed for a purpose that will soon be explained. The dimensions of the excavation 10 will depend upon the purpose thereof.
- a moisture (i.e., water) impermeable grout containment sheet 20 is laid inside the excavation 10 so as to completely cover the bottom thereof. It is important that the grout containment sheet 20 be long enough to initially extend upwardly and over top of the road bed 15 so that the sheet will not be pulled entirely inside the excavation 10 when a heavy panel is laid upon the sheet.
- the grout containment sheet 20 may be carried to the construction site, for example, on a roll of continuous sheet material which is cut to size. Depending upon the size of the excavation 10 , it may be necessary to add one or more additional containment sheets (not shown) which overlap one another in end-to-end alignment.
- the water-impermeable grout containment sheet 20 has a thickness of at last 6 mils.
- the sheet 20 which covers the bottom of the excavation 10 must be manufactured from a material (e.g., polyurethane) that is strong enough to support a load (e.g., a concrete panel) located inside the excavation 10 and prevent water from passing through the sheet.
- a material e.g., polyurethane
- a (e.g., precast) panel 25 that is manufactured from concrete or any other suitable durable and weather-resistant material is transported to and lowered, by means of an overhead crane, or the like, into the excavation.
- the panel 25 sits on the grout containment sheet 20 , and the sheet lies between the panel 25 and the solid surface (e.g., the road bed 15 ) into which the excavation has been cut.
- the ends of the grout containment sheet 20 may then be shortened (i.e., cut) so as to conform to the dimensions of the excavation 10 and the panel 25 that has been lowered therewithin and laid upon the sheet.
- FIG. 3 of the drawings shows a conventional bonding or adhesive filler material 30 , such as grout, or the like, being pumped below the panel 25 within the excavation 10 .
- the grout 30 may be pumped underneath the panel 25 by way of one or more filler tubes 32 that run completely through the panel.
- the filler tubes e.g., 32
- the grout 30 creates a bond to hold the panel 25 in place within the excavation.
- the grout 30 also creates a platform below the panel 25 , whereby the panel can be selectively raised or elevated within the excavation 10 in order to be made level with adjacent panels (e.g., designated 35 ) which are already in place within the excavation.
- the water-impermeable grout containment sheet 20 lies between the grout 30 and the bottom of the excavation 10 that has been cut into the solid surface (i.e., road bed 15 ) to receive the (e.g., concrete) panel 25 .
- the containment sheet 20 establishes a liner or barrier to prevent the grout bonding material 30 from migrating away from the panel 25 and flowing below an adjacent panel 35 .
- portions of the sheet 20 are pulled upwardly to create a peripheral fold (designated 22 in FIGS. 2 and 3 ) which surrounds the panel 25 .
- the water which is mixed into the grout will not pass downwardly through the grout containment sheet 20 to be absorbed by and contaminate the ground around and below the excavation.
- the water-impermeable grout containment sheet 20 creates an envelope around the panel 25 and the grout 30 below the panel 25 so as to prevent the grout from becoming saturated with rain or ground water to which the grout may otherwise be exposed at the construction site. That is to say, grout is known to erode and become weaker as a consequence of either losing water or being mixed with too much water.
- the grout containment sheet 20 maintains the structural integrity and load bearing characteristics of the grout during the time necessary for the grout to be fully cured and hardened.
- the grout containment shed 20 facilitates a removal of the panel 25 from the excavation 10 for subsequent repair or replacement.
- the panel By spraying or coating the bottom of the panel 25 at the time of construction with a conventional liquid bond breaker, the panel can be titled out of the excavation 10 so as to be either replaced with a different panel or cleaned, repaired and returned to the excavation.
- the grout 30 will adhere to the grout containment sheet 20 so as to permit a relatively easy separation of the panel 25 from the grout 30 which remains inside the excavation.
- a plurality of panels like those designated 25 and 35 , which have been lowered into respective excavations or a single continuous excavation, like that designated 10 , can be connected, such as by means of dowel bar couplers (designated 40 in FIG. 3 ), end-to-end and/or side-by-side.
- a continuous roadway may be constructed along a road bed (e.g., 15 ) over which vehicular traffic can travel.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Road Paving Structures (AREA)
Abstract
A water-impermeable grout containment sheet and a method for using the sheet, for example, during the construction of a roadway to support vehicular traffic. An excavation is first cut into a road bed, and a moisture (i.e., water) impermeable grout containment sheet is laid inside the excavation. A plurality of concrete panels are positioned adjacent one another to be coupled together within the excavation, such that at least one of the panels sits on top of the water-impermeable grout containment sheet. Grout is then pumped below the one panel to hold the panel in place within the excavation. The water-impermeable grout containment sheet lies between the grout and the road bed to establish a containment envelope to stop the grout from migrating away from the panel and prevent water from seeping outwardly from the grout into the road bed and into the grout from the excavation.
Description
- 1. Field of the Invention
- This invention relates to a moisture (i.e., water) impermeable grout containment sheet and to a method including the step of locating the sheet within an excavation so as to lie between a (e.g., concrete) panel that has been lowered into the excavation and grout that has been pumped below the panel. The group containment sheet and method have particular application during roadway construction or repair where a plurality of concrete panels are laid in excavations formed in a road bed and connected to one another to support vehicular traffic.
- 2. Background Art
- As new communities are built, it is essential to have a roadway system to link each community with neighboring communities. Therefore, a series of highways and freeways are constructed to support vehicular traffic. A common technique for building such roadways is to lay a number of heavy concrete panels or slabs end-to-end and side-by-side one another. All of the panels must be held in place relative to one another and connected together to establish a smooth and continuous driving surface. The foregoing is often accomplished by first grading a road bed and cutting excavations therein within which the concrete panels are laid.
- Once the concrete panels are located within the excavations, grout is typically pumped below the panels to retain the panels above the road bed. However, with the heavy panels sitting on top, the grout has been known to migrate underneath adjacent panels located within a single excavation or within adjacent excavations. Such migration can adversely affect the stability and level of the concrete panel relative to other panels. Moreover, the water with which the grout is mixed can sometimes seep into and be absorbed by the road bed below the panel. What is even more, the grout lying below the panel within the excavation is susceptible to the negative effects of being exposed to too much water. Such additional water may originate as rain water and/or ground water from the road bed. Until it is completely cured and hardened, which could take up to seven days or more, grout which becomes either too dry or too wet may become brittle or weakened and lose its maximum structural integrity and load-bearing ability.
- Therefore, what would be desirable is a means to prevent the grout that is pumped between a concrete and and the road bed upon which the panel is laid from migrating away from the panel as well as losing its moisture and becoming too wet throughout the road construction project.
- Briefly, and in general terms, a grout containment sheet and method are disclosed having particular application, for example, during roadway construction or repair when excavations are cut into a road bed and (e.g., precast concrete) panels are laid inside the excavations to be connected end-to-end and/or side-by-side. Prior to laying a panel within an excavation, a moisture (i.e., water) impermeable (e.g., polyurethane) grout containment sheet is positioned inside the excavation to cover at least the bottom thereof. The grout containment, sheet must be sufficiently strong to prevent water from passing therethrough.
- The panel is lowered into the excavation so as to lie upon the grout containment sheet. In order to hold the panel in place within the excavation, grout or a similar adhesive bonding material is pumped below the panel such as, for example, by way of filler tubes which run through the panel. Thus, the grout containment sheet lies between the grout and the road bed above which the panel is located. By virtue of the foregoing, the grout containment sheet establishes a containment envelope around the grout throughout the construction project to prevent the grout from migrating away from the panel. At the same time, the grout containment sheet creates a barrier that prevents the grout from both drying out as a consequence of the moisture of the grout being absorbed by the road bed and from becoming too wet as a consequence of being exposed to rain water and ground water. Accordingly, the maximum strength, structural integrity and load-bearing characteristics of the grout upon which the panel is laid and supported can be maintained.
-
FIG. 1 shows an excavation that has been cut into a road bed and a grout containment sheet located within and covering the bottom of the excavation according to a preferred embodiment of this invention; -
FIG. 2 shows a solid panel such as, for example, a precast concrete panel used during the construction of a roadway lowered into the excavation and laying upon the grout containment sheet; and -
FIG. 3 shows an adhesive bonding material (e.g., grout) pumped into the excavation below the panel, such that the grout containment sheet creates a water impermeable containment barrier between the grout and the road bed. - Shown and described herein are a water-impermeable grout containment sheet and a method for using the sheet with a solid (e.g., concrete) panel or slab where the panel is transported to and laid upon the sheet after the sheet is first located inside an excavation that is cut into a solid surface. By way of example, the grout containment sheet and method herein disclosed have particular application during roadway construction and/or repair where a plurality of concrete panels are laid inside one or more excavations so as to be connected end-to-end and/or side-by-side one another. In this same regard, the system and method are also advantageous to facilitating the removal of a panel from its excavation should such removal be required during subsequent roadway maintenance and repair.
- Turning to the drawings,
FIG. 1 shows asingle excavation 10 that has been cut into aroad bed 15. Theexcavation 10 can be cut by means of any of a variety of available construction machinery and plays no role in the present invention. In the event a roadway is being constructed, either a single continuous excavation or a series of adjacent excavations will be cut into the road bed for a purpose that will soon be explained. The dimensions of theexcavation 10 will depend upon the purpose thereof. - In accordance with a preferred embodiment of this invention, a moisture (i.e., water) impermeable
grout containment sheet 20 is laid inside theexcavation 10 so as to completely cover the bottom thereof. It is important that thegrout containment sheet 20 be long enough to initially extend upwardly and over top of theroad bed 15 so that the sheet will not be pulled entirely inside theexcavation 10 when a heavy panel is laid upon the sheet. Thegrout containment sheet 20 may be carried to the construction site, for example, on a roll of continuous sheet material which is cut to size. Depending upon the size of theexcavation 10, it may be necessary to add one or more additional containment sheets (not shown) which overlap one another in end-to-end alignment. By way of example only, the water-impermeablegrout containment sheet 20 has a thickness of at last 6 mils. Thesheet 20 which covers the bottom of theexcavation 10 must be manufactured from a material (e.g., polyurethane) that is strong enough to support a load (e.g., a concrete panel) located inside theexcavation 10 and prevent water from passing through the sheet. - With the
grout containment sheet 20 laid inside theexcavation 10 and covering the bottom thereof, and referring now toFIG. 2 of the drawings, a (e.g., precast)panel 25 that is manufactured from concrete or any other suitable durable and weather-resistant material is transported to and lowered, by means of an overhead crane, or the like, into the excavation. Thus, thepanel 25 sits on thegrout containment sheet 20, and the sheet lies between thepanel 25 and the solid surface (e.g., the road bed 15) into which the excavation has been cut. The ends of thegrout containment sheet 20 may then be shortened (i.e., cut) so as to conform to the dimensions of theexcavation 10 and thepanel 25 that has been lowered therewithin and laid upon the sheet. -
FIG. 3 of the drawings shows a conventional bonding oradhesive filler material 30, such as grout, or the like, being pumped below thepanel 25 within theexcavation 10. Thegrout 30 may be pumped underneath thepanel 25 by way of one ormore filler tubes 32 that run completely through the panel. For example, if thepanel 25 is a precast concrete panel, the filler tubes (e.g., 32) are typically embedded within the panel during the manufacturing (i.e., casting) process. Thegrout 30 creates a bond to hold thepanel 25 in place within the excavation. Moreover, thegrout 30 also creates a platform below thepanel 25, whereby the panel can be selectively raised or elevated within theexcavation 10 in order to be made level with adjacent panels (e.g., designated 35) which are already in place within the excavation. - Accordingly, it may be appreciated that the water-impermeable
grout containment sheet 20 lies between thegrout 30 and the bottom of theexcavation 10 that has been cut into the solid surface (i.e., road bed 15) to receive the (e.g., concrete)panel 25. By virtue of the foregoing, thecontainment sheet 20 establishes a liner or barrier to prevent the grout bondingmaterial 30 from migrating away from thepanel 25 and flowing below anadjacent panel 35. To this end, portions of thesheet 20 are pulled upwardly to create a peripheral fold (designated 22 inFIGS. 2 and 3 ) which surrounds thepanel 25. Thus, the water which is mixed into the grout will not pass downwardly through thegrout containment sheet 20 to be absorbed by and contaminate the ground around and below the excavation. In this same regard, and as another important advantage, the water-impermeablegrout containment sheet 20 creates an envelope around thepanel 25 and thegrout 30 below thepanel 25 so as to prevent the grout from becoming saturated with rain or ground water to which the grout may otherwise be exposed at the construction site. That is to say, grout is known to erode and become weaker as a consequence of either losing water or being mixed with too much water. However, thegrout containment sheet 20 maintains the structural integrity and load bearing characteristics of the grout during the time necessary for the grout to be fully cured and hardened. - What is even still more, the
grout containment shed 20 facilitates a removal of thepanel 25 from theexcavation 10 for subsequent repair or replacement. By spraying or coating the bottom of thepanel 25 at the time of construction with a conventional liquid bond breaker, the panel can be titled out of theexcavation 10 so as to be either replaced with a different panel or cleaned, repaired and returned to the excavation. In this case, thegrout 30 will adhere to thegrout containment sheet 20 so as to permit a relatively easy separation of thepanel 25 from thegrout 30 which remains inside the excavation. - As previously explained, a plurality of panels, like those designated 25 and 35, which have been lowered into respective excavations or a single continuous excavation, like that designated 10, can be connected, such as by means of dowel bar couplers (designated 40 in
FIG. 3 ), end-to-end and/or side-by-side. Thus, a continuous roadway may be constructed along a road bed (e.g., 15) over which vehicular traffic can travel.
Claims (8)
1. A method for installing at least a first panel on a surface, said method comprising the steps of:
placing a moisture-impermeable sheet over the surface;
laying the first panel on top of the moisture-impermeable sheet; and
pumping an adhesive bonding material between the first panel and the moisture-impermeable sheet such that said sheet lies between the adhesive bonding material and the surface over which the sheet is placed.
2. The method recited in claim 1 , comprising the additional step of cutting an excavation into a road bed such that said excavation forms the surface upon which said moisture-impermeable sheet is placed.
3. The method recited in claim 2 , comprising the additional step of positioning said moisture-impermeable sheet within the excavation so as to form a containment envelope around the adhesive bonding material for preventing said bonding material from migrating away from the first panel.
4. The method recited in claim 2 , comprising the additional step of manufacturing said moisture-impermeable sheet from a material that is impervious to the passage of water therethrough so as to separate the adhesive bonding material from the excavation.
5. The method recited in claim 2 , comprising the additional steps of laying a second panel within the excavation adjacent said first panel; and coupling said first and second panels to one another to establish a roadway to support vehicular traffic thereover.
6. The method recited in claim 1 , wherein said adhesive bonding material is grout.
7. The method recited in claim 1 , comprising the additional step of manufacturing said first panel from concrete.
8. A method for constructing a roadway to support vehicular traffic thereover, said method comprising the steps of:
cutting an excavation into a road bed;
placing a moisture-impermeable sheet inside the excavation;
laying a plurality of concrete panels adjacent one another within the excavation such that at least a first of said concrete panels sits on top of said moisture-impermeable sheet;
pumping grout between the first concrete panel and the moisture-impermeable sheet such that said sheet creates a barrier between the grout and the excavation for preventing the grout from migrating away from the first concrete panel within the excavation; and
coupling said plurality of adjacent concrete panels one to the other to establish said roadway.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/917,941 US20140369750A1 (en) | 2013-06-14 | 2013-06-14 | Grout containment sheet and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/917,941 US20140369750A1 (en) | 2013-06-14 | 2013-06-14 | Grout containment sheet and method |
Publications (1)
Publication Number | Publication Date |
---|---|
US20140369750A1 true US20140369750A1 (en) | 2014-12-18 |
Family
ID=52019345
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/917,941 Abandoned US20140369750A1 (en) | 2013-06-14 | 2013-06-14 | Grout containment sheet and method |
Country Status (1)
Country | Link |
---|---|
US (1) | US20140369750A1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150267358A1 (en) * | 2014-03-19 | 2015-09-24 | Mark Sanders | Pre-cast concrete road repair panel |
US20150284915A1 (en) * | 2014-03-19 | 2015-10-08 | Mark E. Sanders | Leveling plate apparatus for a road repair system |
CN109024130A (en) * | 2018-08-30 | 2018-12-18 | 泰山学院 | A kind of floor tile and laying method |
CN112681087A (en) * | 2021-01-14 | 2021-04-20 | 刘为浩 | Automatic tectorial membrane concrete maintenance device that permeates water |
CN114875732A (en) * | 2021-12-17 | 2022-08-09 | 长沙理工大学 | Embankment settlement prevention structure and method for expressway reconstruction and extension project |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US169005A (en) * | 1875-10-19 | Improvement in pavements | ||
US1330139A (en) * | 1917-04-26 | 1920-02-10 | Ward Carpenter And Company Inc | Roadway or pavement and method of constructing same |
US1664638A (en) * | 1926-02-23 | 1928-04-03 | Joseph H Mitter | Floor construction |
US2737092A (en) * | 1952-07-19 | 1956-03-06 | Clarence U Gramelspacher | Rubber-coated plywood for roadbed on highways |
US3909143A (en) * | 1971-05-18 | 1975-09-30 | Romanski Lon H | Roadway construction and method therefor |
US5586834A (en) * | 1994-04-08 | 1996-12-24 | Otaru Development And Construction Department Of Hokkaido Development Bureau | Joint structure for coupling precast concrete pavement slabs |
US5957619A (en) * | 1995-10-12 | 1999-09-28 | Taisei Rotec Corporation | Method of constructing block pavement |
US6146051A (en) * | 1994-10-14 | 2000-11-14 | Conventry University | Paving system for spillage and flood management |
US20010002497A1 (en) * | 1999-04-12 | 2001-06-07 | Alberto M. Scuero | Geocomposite system for roads and bridges and construction method |
US7059800B2 (en) * | 2001-02-28 | 2006-06-13 | Owens Corning Fiberglas Technology, Inc. | Method of reinforcing and waterproofing a paved surface |
US7134805B2 (en) * | 2004-04-01 | 2006-11-14 | Kwik Slab, Llc | Precast concrete slab system and method therefor |
US8186117B2 (en) * | 2008-05-27 | 2012-05-29 | Eren Tumer H | System for creating a decking/flooring and a method for installing same |
-
2013
- 2013-06-14 US US13/917,941 patent/US20140369750A1/en not_active Abandoned
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US169005A (en) * | 1875-10-19 | Improvement in pavements | ||
US1330139A (en) * | 1917-04-26 | 1920-02-10 | Ward Carpenter And Company Inc | Roadway or pavement and method of constructing same |
US1664638A (en) * | 1926-02-23 | 1928-04-03 | Joseph H Mitter | Floor construction |
US2737092A (en) * | 1952-07-19 | 1956-03-06 | Clarence U Gramelspacher | Rubber-coated plywood for roadbed on highways |
US3909143A (en) * | 1971-05-18 | 1975-09-30 | Romanski Lon H | Roadway construction and method therefor |
US5586834A (en) * | 1994-04-08 | 1996-12-24 | Otaru Development And Construction Department Of Hokkaido Development Bureau | Joint structure for coupling precast concrete pavement slabs |
US6146051A (en) * | 1994-10-14 | 2000-11-14 | Conventry University | Paving system for spillage and flood management |
US5957619A (en) * | 1995-10-12 | 1999-09-28 | Taisei Rotec Corporation | Method of constructing block pavement |
US20010002497A1 (en) * | 1999-04-12 | 2001-06-07 | Alberto M. Scuero | Geocomposite system for roads and bridges and construction method |
US7059800B2 (en) * | 2001-02-28 | 2006-06-13 | Owens Corning Fiberglas Technology, Inc. | Method of reinforcing and waterproofing a paved surface |
US7134805B2 (en) * | 2004-04-01 | 2006-11-14 | Kwik Slab, Llc | Precast concrete slab system and method therefor |
US8186117B2 (en) * | 2008-05-27 | 2012-05-29 | Eren Tumer H | System for creating a decking/flooring and a method for installing same |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150267358A1 (en) * | 2014-03-19 | 2015-09-24 | Mark Sanders | Pre-cast concrete road repair panel |
US20150284915A1 (en) * | 2014-03-19 | 2015-10-08 | Mark E. Sanders | Leveling plate apparatus for a road repair system |
US9546454B2 (en) * | 2014-03-19 | 2017-01-17 | Mark Sanders | Pre-cast concrete road repair panel |
US9556566B2 (en) * | 2014-03-19 | 2017-01-31 | Mark E. Sanders | Leveling plate apparatus for a road repair system |
CN109024130A (en) * | 2018-08-30 | 2018-12-18 | 泰山学院 | A kind of floor tile and laying method |
CN112681087A (en) * | 2021-01-14 | 2021-04-20 | 刘为浩 | Automatic tectorial membrane concrete maintenance device that permeates water |
CN114875732A (en) * | 2021-12-17 | 2022-08-09 | 长沙理工大学 | Embankment settlement prevention structure and method for expressway reconstruction and extension project |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8474080B2 (en) | Construction method of steel composition girder bridge | |
US9874036B2 (en) | Prefabricated, deconstructable, multistory building construction | |
CN104631349B (en) | A kind of dismounting of urban viaduct steel box-girder and deposit method | |
US20140369750A1 (en) | Grout containment sheet and method | |
CN104895089B (en) | Basement floor and the construction method of the cooperative permanent support system of support pile | |
EP3099859B1 (en) | Method for waterproofing railway bridges | |
KR101036277B1 (en) | Expansion joint waterproof material of structure including road and bridge, and constructing method of expansion joint part using this | |
CN108798059A (en) | A kind of old masonry seismic reinforcing structure and construction method | |
CN109648696A (en) | Side slope precast lattice beam of reinforcing bar connection and preparation method thereof and construction method | |
CN110863405B (en) | Assembled photovoltaic power generation-high-performance concrete pavement structure and construction method | |
CA1122021A (en) | Method of filling a hole in the ground | |
CN105888281A (en) | Method for utilizing jacking storey-adding technique to promote integrated function of community | |
CN113502835A (en) | Wet cellular assembled gridwork roof beam slope protection structure of connecting | |
CN108708290A (en) | The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit | |
CN105780624B (en) | composite structure layer and its laying method | |
RU84857U1 (en) | HIGHWAY | |
KR100214388B1 (en) | Bridge repairing method using the existing super structure | |
CN114059414A (en) | Overhead superposed type tunnel structure suitable for frozen soil area and construction method | |
CN110821021A (en) | Floor slab capable of being installed rapidly | |
US11332897B2 (en) | Bridge support system | |
AU2016225892B2 (en) | Modular bridge, modular component and method for constructing modular bridge | |
CN115075076B (en) | High-fill and low-soil composite roadbed structure and construction method | |
CN110820468B (en) | Multifunctional assembled photovoltaic power generation pavement and construction method | |
CN106836231A (en) | The assembling constructing method of big cross section precast construction in the deep big foundation pit of soft clay area | |
CN108571080B (en) | A kind of adjustable deformation modularization skin-type composite water-proof construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |