CN107705055A - Power network technology innovation project backlog control method based on bill of quantities - Google Patents

Power network technology innovation project backlog control method based on bill of quantities Download PDF

Info

Publication number
CN107705055A
CN107705055A CN201711190230.9A CN201711190230A CN107705055A CN 107705055 A CN107705055 A CN 107705055A CN 201711190230 A CN201711190230 A CN 201711190230A CN 107705055 A CN107705055 A CN 107705055A
Authority
CN
China
Prior art keywords
project
equipment
data
import
power grid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711190230.9A
Other languages
Chinese (zh)
Inventor
罗汉武
张秋伟
温立斌
刘振
张希兵
李东明
孙鑫
姜国义
刘海波
李文波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Technology Innovation Engineering Institute of CAS
State Grid Eastern Inner Mongolia Power Co Ltd
Original Assignee
Hefei Technology Innovation Engineering Institute of CAS
State Grid Eastern Inner Mongolia Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Technology Innovation Engineering Institute of CAS, State Grid Eastern Inner Mongolia Power Co Ltd filed Critical Hefei Technology Innovation Engineering Institute of CAS
Priority to CN201711190230.9A priority Critical patent/CN107705055A/en
Publication of CN107705055A publication Critical patent/CN107705055A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及基于工程量清单的电网技改工程储备管理方法,与现有技术相比解决了暂无利用工程量清单实现技改工程储备管理的缺陷。本发明包括以下步骤:基础数据初始化;项目建议书的生成和数据导入;项目建议书的审批;校核电网技改工程价费;审核电网技改工程造价。本发明将基于工程量清单的造价单导入项目储备信息,能够根据工程量清单计价模式,实现电网技改工程项目储备管理。

The invention relates to a method for managing reserves of power grid technical upgrading projects based on bill of quantities, and solves the defect that there is no use of bill of quantities to realize reserve management of technical upgrading projects as compared with the prior art. The invention comprises the following steps: initializing basic data; generating project proposals and data import; examining and approving project proposals; The invention imports the cost list based on the bill of engineering quantity into the project reserve information, and can realize the project reserve management of the power grid technical transformation project according to the bill of engineering quantity pricing mode.

Description

基于工程量清单的电网技改工程储备管理方法Reserve management method for power grid technical upgrading project based on bill of quantities

技术领域technical field

本发明涉及数据处理技术领域,具体来说是基于工程量清单的电网技改工程储备管理方法。The invention relates to the technical field of data processing, in particular to a method for managing reserves of power grid technical renovation projects based on bill of quantities.

背景技术Background technique

电网技改工程储备管理是电网技改工程全过程管理的重要环节,是工程质量和成本控制的基础和保障,将直接影响电力施工企业的经济效益。当前,由于电网技改工程储备管理信息数据量大、来源渠道多、变动频繁,存在着电网技改管控过程中储备项目统计分析困难、更新滞后、储备与预算、招投标等之间的信息有偏差等问题,很难高效、合理管控整个电网技改工程进度、成本等情况。此外,大部分储备项目编制还存在着技改工程项目纸质申报、筛选、审核和查询等人工方式,没有对应的电网技改工程储备管理计算机系统对各类技改工程项目储备情况进行跟踪管控。Power grid technical upgrading project reserve management is an important part of the whole process management of power grid technical upgrading project, and it is the basis and guarantee of project quality and cost control, which will directly affect the economic benefits of power construction enterprises. At present, due to the large amount of reserve management information data, many sources and channels, and frequent changes in the technical transformation project of the power grid, there are difficulties in statistical analysis of reserve projects in the process of technical transformation control of the power grid, update lags, information gaps between reserves and budgets, bidding, etc. Deviation and other issues, it is difficult to efficiently and reasonably control the progress and cost of the entire power grid technical transformation project. In addition, most reserve projects still have manual methods such as paper application, screening, review and query of technical upgrading projects, and there is no corresponding power grid technical upgrading project reserve management computer system to track and control the reserve status of various technical upgrading projects .

而工程量清单作为一种全新的计价方式,采用综合单价,以市场价格进行成本预算,明确而详细地反映了技改工程的实物消耗及其它有关费用,包括了人工、材料、机械、管理费和利润,具有量价分离与风险各担等特点,便于合同价格调整。As a brand-new pricing method, the bill of quantities adopts comprehensive unit price and carries out cost budget at market price, which clearly and detailedly reflects the physical consumption and other related expenses of technical upgrading projects, including labor, materials, machinery, and management fees It has the characteristics of separation of quantity and price and separate risks, which is convenient for contract price adjustment.

那么,如何将基于工程量清单来实现各类技改工程项目储备情况的跟踪管控已经成为急需解决的技术问题。Then, how to realize the tracking and control of the reserves of various technical renovation projects based on the bill of quantities has become an urgent technical problem to be solved.

发明内容Contents of the invention

本发明的目的是为了解决现有技术中暂无利用工程量清单实现技改工程储备管理的缺陷,提供一种基于工程量清单的电网技改工程储备管理方法来解决上述问题。The purpose of the present invention is to solve the defect in the prior art that there is no use of the bill of quantities to realize the reserve management of the technical renovation project, and to provide a method for managing the reserve of the technical renovation project of the power grid based on the bill of quantities to solve the above problems.

为了实现上述目的,本发明的技术方案如下:In order to achieve the above object, the technical scheme of the present invention is as follows:

基于工程量清单的电网技改工程储备管理方法,包括以下步骤:The reserve management method of power grid technical upgrading project based on the bill of quantities includes the following steps:

基础数据初始化,将电网技改工程储备项目的各种基础数据库导入基础数据管理库,其包括工程量清单标准库、技改工程成本定额库、主材库及设备库、项目储备库、立项依据库、业务流程文件;Basic data initialization, importing various basic databases of power grid technical upgrading project reserve projects into the basic data management database, including the standard library of the bill of quantities, the cost quota database of technical upgrading projects, the main material library and equipment library, the project reserve library, and the basis for project establishment Libraries, business process files;

项目建议书的生成和数据导入,填报技改工作量和项目预算,生成项目建议书并导入数据;Generating project proposals and importing data, filling in technical transformation workload and project budget, generating project proposals and importing data;

项目建议书的审批,通过工单信息,对提交的项目工单进行建议书审批和填写意见,审批完后上报进行价费校核;Approval of the project proposal, through the work order information, to approve the proposal and fill in the comments for the submitted project work order, and report it for price verification after approval;

校核电网技改工程价费,对提交的项目建议书且项目建议书状态为审批通过的进行价费校核、出具价费校核意见;Check the price and fee of the power grid technical transformation project, and conduct price and fee check and issue a price and fee check opinion for the submitted project proposal and the status of the project proposal is approved;

其中价费校核的方法为:选择工单信息,对提交的项目工单且工单状态市公司审批通过的进行价费校核和填写意见;如果造价单数据都正确,填写校核意见,选择校核通过,保存;如果造价单数据不正确,在对应数据的红色方框内,填写正确标准值或修改意见,选择校核不通过;The method of checking the price and fee is: select the work order information, check the price and fill in the comments for the submitted project work order and the work order status has been approved by the city company; if the cost list data is correct, fill in the check opinion, Select to pass the verification and save; if the cost sheet data is incorrect, fill in the correct standard value or modification opinion in the red box of the corresponding data, and select not to pass the verification;

审核电网技改工程造价,对项目建议书进行技改工程造价审核、出具造价审核意见并上报,形成正式的项目储备。Review the cost of the technical transformation project of the power grid, conduct a cost review of the technical transformation project on the project proposal, issue and report the cost review opinion, and form a formal project reserve.

所述填报技改工作量和项目预算为非可研性项目的填入,其包括以下步骤:导入项目基本信息,包括项目名称、项目起止时间、有无预算、有无拟拆除设备清单、项目类别、专业细分、电压等级,编制人员、编制时间、审核、审核时间、批准和批准时间;项目名称包含电压等级,并以指定改造、更换或建设为命名结束;The technical transformation workload and project budget described above are for non-feasibility research projects, which include the following steps: import basic project information, including project name, project start and end time, whether there is a budget, whether there is a list of equipment to be dismantled, the project Category, professional subdivision, voltage level, compiler, compilation time, review, review time, approval and approval time; the project name includes the voltage level, and ends with the designation of renovation, replacement or construction;

如果非可研项目是可预算的,项目工作量填报完成后导入预算数据;项目类别包括电网一次、二次系统和其他;专业细分包括输电、变电和配电;If the non-feasibility study project is budgetable, import the budget data after the project workload is completed; project category includes power grid primary system, secondary system and others; professional subdivision includes power transmission, power transformation and power distribution;

如果有拟拆除设备清单,则新增设备清单、或直接导入拟拆除设备或从PMS中导入,自动生成设备现状、存在问题等主体信息;If there is a list of equipment to be removed, add a new list of equipment, or directly import the equipment to be removed or import it from the PMS, and automatically generate the main information such as the current status of the equipment and existing problems;

拟拆除设备清单;包括“导入拆除设备”和“从PMS导入”两种导入拟拆除设备清单;List of equipment to be dismantled; including "importing dismantling equipment" and "importing from PMS" two imported lists of equipment to be dismantled;

对拆除设备清单中的每个设备的明细信息进行编辑,包括所属线路、设备名称、设备类型、电压等级、设备型号、投运日期、数量、计量单位、存在问题、技术实施方案、设备运行情况、安全评价、周期成本评价、效能评价;Edit the detailed information of each equipment in the dismantled equipment list, including the line to which it belongs, equipment name, equipment type, voltage level, equipment model, date of commissioning, quantity, unit of measurement, existing problems, technical implementation plan, and equipment operation , safety evaluation, cycle cost evaluation, performance evaluation;

导入实施必要性材料、项目方案和不可测算计算表,Import implementation necessary materials, project plans and non-calculated calculation tables,

对不可测算计算表进行量化分析,Quantitative analysis of non-measurable calculation tables,

量化分析的参考公式为:类似项目实际投资成本*项目投资规模的修正系数*通货膨胀率,其中,项目投资规模的修正系数=本项目投资线路长度或变电容量/类似项目投资线路长度或变电容量;The reference formula for quantitative analysis is: actual investment cost of similar projects * correction coefficient of project investment scale * inflation rate, where, correction coefficient of project investment scale = length of investment line or variable capacity of this project / length of investment line or variable capacity of similar projects capacitance;

通货膨胀率=1+类似项目至本项目之间各年度CPI之和,通货膨胀率以110%为标准。Inflation rate = 1+ the sum of CPI in each year between similar projects and this project, and the inflation rate is 110% as the standard.

所述生成项目建议书并导入数据包括以下步骤:The generating project proposal and importing data include the following steps:

生成项目建议书,定义项目建议书包括项目总投资、设备及材料合计,其中,项目总投资为设备及材料购置费、建筑工程费、安装工程费、其它费用的总和,设备及材料合计由数量×单位获取,保留小数点后两位有效数字;Generate a project proposal and define that the project proposal includes the total project investment, total equipment and materials, where the total project investment is the sum of equipment and material purchase fees, construction engineering fees, installation engineering fees, and other expenses, and the total equipment and materials are determined by the quantity × unit acquisition, two valid digits after the decimal point are reserved;

导入数据,Import Data,

导出项目工单,按照查询条件导出项目汇总一览表及每个项目的项目建议书和造价单,查询条件包括基本信息、拟拆除设备信息、评估鉴定信息、附图;Export the project work order, export the project summary list and the project proposal and cost list of each project according to the query conditions. The query conditions include basic information, equipment information to be dismantled, evaluation and identification information, and drawings;

导出格式分excel和系统.data格式,excel格式的用于用户查看,.data格式用于系统内部流转;选择导出格式为系统格式时,选择按“专业细分、单位”进行导出多个文件,并进行分发;选择按单位进行导出时,可选择按市或按县导出对应单位的多个data文件,选择按专业细分时,根据具体的细分专业导出对应的data文件;如果导出方式都不选择时,统一导出单一的data文件;导出结果分为对上上报和对下批复分别导入项目工单;The export format is divided into excel and system .data format, the excel format is used for user viewing, and the .data format is used for internal circulation in the system; when the export format is selected as the system format, select to export multiple files by "professional segmentation, unit", And distribute it; when exporting by unit, you can choose to export multiple data files of the corresponding unit by city or county; when you choose to subdivide by specialty, export the corresponding data file according to the specific subdivision; When not selected, a single data file is uniformly exported; the export results are divided into upper reporting and lower approval respectively imported into project work orders;

导入项目工单,选择由系统产生的data文件,解析data中存在的工单信息,选择加载所需要的工单信息。Import the project work order, select the data file generated by the system, analyze the work order information in the data, and select and load the required work order information.

有益效果Beneficial effect

本发明的基于工程量清单的电网技改工程储备管理方法,与现有技术相比解决了电网技改管控过程中储备项目统计分析困难、更新滞后、储备与预算、招投标等之间的信息有偏差等问题。Compared with the prior art, the reserve management method of power grid technical transformation project based on the bill of quantities of the present invention solves the difficulty in statistical analysis of reserve items, update lag, information between reserve and budget, bidding, etc. in the process of power grid technical transformation management and control There are problems such as deviation.

本发明将基于工程量清单的造价单导入项目储备信息,能够根据工程量清单计价模式,实现电网技改工程项目储备管理,包括项目建议书填报、审批,价费校核、造价审核和审批,实现造价单的快速导入、统计分析的自动生成和导出,提高了储备管理的工作效率和准确率,能有效的避免由于项目数据量大、来源渠道多、变动频繁等给储备管理带来的问题,有利于统一、规范项目储备管理,便于跟踪电网技改项目在整个技改管控过程中的进度、资金消耗等情况,为电网技改工程项目的顺利进行提供有力保障。The invention imports the cost list based on the bill of quantities into the project reserve information, and can realize the project reserve management of the power grid technical transformation project according to the bill of quantities valuation mode, including project proposal filling, approval, price verification, cost review and approval, Realize the rapid import of cost list, automatic generation and export of statistical analysis, improve the efficiency and accuracy of reserve management, and can effectively avoid problems caused by large project data, multiple source channels, frequent changes, etc. , It is conducive to the unification and standardization of project reserve management, and it is convenient to track the progress and capital consumption of power grid technical transformation projects in the entire technical transformation control process, and provide a strong guarantee for the smooth progress of power grid technical transformation projects.

附图说明Description of drawings

图1为本发明的方法顺序图。Fig. 1 is a method sequence diagram of the present invention.

具体实施方式detailed description

为使对本发明的结构特征及所达成的功效有更进一步的了解与认识,用以较佳的实施例及附图配合详细的说明,说明如下:In order to have a further understanding and understanding of the structural features of the present invention and the achieved effects, the preferred embodiments and accompanying drawings are used for a detailed description, as follows:

如图1所示,本发明所述的基于工程量清单的电网技改工程储备管理方法,包括以下步骤:As shown in Figure 1, the method for managing power grid technical renovation project reserves based on the bill of quantities of the present invention includes the following steps:

第一步,基础数据初始化。将电网技改工程储备项目的各种基础数据库导入基础数据管理库,其包括工程量清单标准库、技改工程成本定额库、主材库及设备库、项目储备库、立项依据库、业务流程文件。The first step is to initialize the basic data. Import various basic databases of power grid technical transformation project reserve projects into the basic data management database, including the standard database of the bill of quantities, the cost quota database of technical transformation projects, the main material database and equipment database, the project reserve database, the project basis database, and the business process document.

第二步,项目建议书的生成和数据导入。填报技改工作量和项目预算,生成项目建议书并导入数据。其中,填报技改工作量和项目预算包括以下步骤:The second step is the generation of project proposals and data import. Fill in the technical transformation workload and project budget, generate project proposals and import data. Among them, filling in the technical transformation workload and project budget includes the following steps:

根据电网技改工程项目定义,其中200万以下的项目为非可研性项目。非可研性项目的填入步骤如下:According to the definition of power grid technical transformation project, the projects below 2 million are non-feasibility projects. The filling steps of non-feasibility research projects are as follows:

A、导入项目基本信息,包括项目名称、项目起止时间、有无预算、有无拟拆除设备清单、项目类别、专业细分、电压等级,编制人员、编制时间、审核、审核时间、批准和批准时间;项目名称包含电压等级,并以指定改造、更换或建设为命名结束;A. Import the basic information of the project, including project name, project start and end time, whether there is a budget, whether there is a list of equipment to be dismantled, project category, professional subdivision, voltage level, preparation personnel, preparation time, review, review time, approval and approval Time; the project name includes the voltage level and ends with the designation of renovation, replacement or construction;

如果非可研项目是可预算的,项目工作量填报完成后导入预算数据;项目类别包括电网一次、二次系统和其他;专业细分包括输电、变电和配电。If the non-feasibility study project is budgetable, import the budget data after the project workload is completed; the project category includes power grid primary system, secondary system and others; professional subdivision includes power transmission, power transformation and power distribution.

B、如果有拟拆除设备清单,则新增设备清单、或直接导入拟拆除设备或从PMS中导入,自动生成设备现状、存在问题等主体信息;B. If there is a list of equipment to be removed, add a new list of equipment, or directly import the equipment to be removed or import it from PMS, and automatically generate the main information such as the current status of the equipment and existing problems;

拟拆除设备清单;包括“导入拆除设备”和“从PMS导入”两种导入拟拆除设备清单。List of equipment to be dismantled; including "importing dismantling equipment" and "importing from PMS".

C、对拆除设备清单中的每个设备的明细信息进行编辑,包括所属线路、设备名称、设备类型、电压等级、设备型号、投运日期、数量、计量单位、存在问题、技术实施方案、设备运行情况、安全评价、周期成本评价、效能评价。C. Edit the detailed information of each equipment in the dismantled equipment list, including the line to which it belongs, equipment name, equipment type, voltage level, equipment model, date of commissioning, quantity, unit of measurement, existing problems, technical implementation plan, equipment Operation status, safety evaluation, cycle cost evaluation, performance evaluation.

D、导入实施必要性材料、项目方案和不可测算计算表。D. Import necessary material for implementation, project plan and uncalculated calculation table.

E、对不可测算计算表进行量化分析,E. Quantitative analysis of non-measurable calculation tables,

量化分析的参考公式为:类似项目实际投资成本*项目投资规模的修正系数*通货膨胀率,其中,项目投资规模的修正系数=本项目投资线路长度或变电容量/类似项目投资线路长度或变电容量;The reference formula for quantitative analysis is: actual investment cost of similar projects * correction coefficient of project investment scale * inflation rate, where, correction coefficient of project investment scale = length of investment line or variable capacity of this project / length of investment line or variable capacity of similar projects capacitance;

通货膨胀率=1+类似项目至本项目之间各年度CPI之和,通货膨胀率以110%为标准。Inflation rate = 1+ the sum of CPI in each year between similar projects and this project, and the inflation rate is 110% as the standard.

其中,生成项目建议书并导入数据包括以下步骤:Among them, generating project proposals and importing data includes the following steps:

(1)生成项目建议书,定义项目建议书包括项目总投资、设备及材料合计,其中,项目总投资为设备及材料购置费、建筑工程费、安装工程费、其它费用的总和,设备及材料合计由数量×单位获取,保留小数点后两位有效数字。(1) Generate a project proposal and define that the project proposal includes the total project investment, equipment and materials. Among them, the total project investment is the sum of equipment and material purchase fees, construction engineering fees, installation engineering fees, and other expenses, equipment and materials The total is obtained by quantity × unit, and there are two valid figures after the decimal point.

(2)导入数据,(2) import data,

A、导出项目工单,按照查询条件导出项目汇总一览表及每个项目的项目建议书和造价单,查询条件包括基本信息、拟拆除设备信息、评估鉴定信息、附图;A. Export the project work order, export the project summary list and the project proposal and cost list of each project according to the query conditions. The query conditions include basic information, equipment information to be dismantled, evaluation and identification information, and drawings;

导出格式分excel和系统.data格式,excel格式的用于用户查看,.data格式用于系统内部流转;选择导出格式为系统格式时,选择按“专业细分、单位”进行导出多个文件,并进行分发;选择按单位进行导出时,可选择按市或按县导出对应单位的多个data文件,选择按专业细分时,根据具体的细分专业导出对应的data文件;如果导出方式都不选择时,统一导出单一的data文件;导出结果分为对上上报和对下批复分别导入项目工单;The export format is divided into excel and system .data format, the excel format is used for user viewing, and the .data format is used for internal circulation in the system; when the export format is selected as the system format, select to export multiple files by "professional segmentation, unit", And distribute it; when exporting by unit, you can choose to export multiple data files of the corresponding unit by city or county; when you choose to subdivide by specialty, export the corresponding data file according to the specific subdivision; When not selected, a single data file is uniformly exported; the export results are divided into upper reporting and lower approval respectively imported into project work orders;

B、导入项目工单,选择由系统产生的data文件,解析data中存在的工单信息,选择加载所需要的工单信息。B. Import the project work order, select the data file generated by the system, analyze the work order information in the data, and select and load the required work order information.

第三步,项目建议书的审批。,通过工单信息,对提交的项目工单进行建议书审批和填写意见,审批完后上报进行价费校核。The third step is the approval of the project proposal. , Through the work order information, approve the proposal and fill in the comments for the submitted project work order, and report it for price verification after approval.

第四步,校核电网技改工程价费,对提交的项目建议书且项目建议书状态为审批通过的进行价费校核、出具价费校核意见。The fourth step is to check the price and fee of the technical transformation project of the power grid. For the submitted project proposal and the status of the project proposal is approved, the price and fee will be checked and the price and fee check opinion will be issued.

其中价费校核的方法为:选择工单信息,对提交的项目工单且工单状态市公司审批通过的进行价费校核和填写意见;如果造价单数据都正确,填写校核意见,选择校核通过,保存;如果造价单数据不正确,在对应数据的红色方框内,填写正确标准值或修改意见,选择校核不通过。The method of checking the price and fee is: select the work order information, check the price and fill in the comments for the submitted project work order and the work order status has been approved by the city company; if the cost list data is correct, fill in the check opinion, Select pass the verification and save it; if the cost sheet data is incorrect, fill in the correct standard value or modification opinion in the red box of the corresponding data, and choose not to pass the verification.

第五步,审核电网技改工程造价,对项目建议书进行技改工程造价审核、出具造价审核意见并上报,形成正式的项目储备。The fifth step is to review the cost of the technical transformation project of the power grid, conduct a technical transformation project cost review on the project proposal, issue the cost review opinion and report it, and form a formal project reserve.

以上显示和描述了本发明的基本原理、主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是本发明的原理,在不脱离本发明精神和范围的前提下本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明的范围内。本发明要求的保护范围由所附的权利要求书及其等同物界定。The basic principles, main features and advantages of the present invention have been shown and described above. Those skilled in the art should understand that the present invention is not limited by the above-mentioned embodiments. What are described in the above-mentioned embodiments and the description are only the principles of the present invention. Variations and improvements, which fall within the scope of the claimed invention. The scope of protection required by the present invention is defined by the appended claims and their equivalents.

Claims (3)

1.一种基于工程量清单的电网技改工程储备管理方法,其特征在于,包括以下步骤:1. A method for managing power grid technical renovation project reserves based on bill of quantities, characterized in that, comprising the following steps: 11)基础数据初始化,将电网技改工程储备项目的各种基础数据库导入基础数据管理库,其包括工程量清单标准库、技改工程成本定额库、主材库及设备库、项目储备库、立项依据库、业务流程文件;11) Basic data initialization, importing various basic databases of power grid technical upgrading project reserve projects into the basic data management database, including the bill of quantities standard database, technical upgrading project cost quota database, main material database and equipment database, project reserve database, Project basis library, business process documents; 12)项目建议书的生成和数据导入,填报技改工作量和项目预算,生成项目建议书并导入数据;12) Generation of project proposals and data import, fill in the workload of technical transformation and project budget, generate project proposals and import data; 13)项目建议书的审批,通过工单信息,对提交的项目工单进行建议书审批和填写意见,审批完后上报进行价费校核;13) Examination and approval of project proposals, through the work order information, review and fill in the proposals for the submitted project work orders, and submit the report for price verification after approval; 14)校核电网技改工程价费,对提交的项目建议书且项目建议书状态为审批通过的进行价费校核、出具价费校核意见;14) Check the price and fee of the technical transformation project of the power grid, and conduct price and fee check and issue a price and fee check opinion for the submitted project proposal and the status of the project proposal is approved; 其中价费校核的方法为:选择工单信息,对提交的项目工单且工单状态市公司审批通过的进行价费校核和填写意见;如果造价单数据都正确,填写校核意见,选择校核通过,保存;如果造价单数据不正确,在对应数据的红色方框内,填写正确标准值或修改意见,选择校核不通过;The method of checking the price and fee is: select the work order information, check the price and fill in the comments for the submitted project work order and the work order status has been approved by the city company; if the cost list data is correct, fill in the check opinion, Select to pass the verification and save; if the cost sheet data is incorrect, fill in the correct standard value or modification opinion in the red box of the corresponding data, and select not to pass the verification; 15)审核电网技改工程造价,对项目建议书进行技改工程造价审核、出具造价审核意见并上报,形成正式的项目储备。15) Review the cost of the power grid technical transformation project, review the project proposal for the technical transformation project cost, issue and report the cost review opinion, and form a formal project reserve. 2.根据权利要求1所述的基于工程量清单的电网技改工程储备管理方法,其特征在于,所述填报技改工作量和项目预算为非可研性项目的填入,其包括以下步骤:2. The method for managing power grid technical renovation project reserves based on bill of quantities according to claim 1, characterized in that the technical renovation workload and project budget are filled in for non-feasibility projects, and it includes the following steps : 21)导入项目基本信息,包括项目名称、项目起止时间、有无预算、有无拟拆除设备清单、项目类别、专业细分、电压等级,编制人员、编制时间、审核、审核时间、批准和批准时间;项目名称包含电压等级,并以指定改造、更换或建设为命名结束;21) Import the basic information of the project, including project name, project start and end time, whether there is a budget, whether there is a list of equipment to be dismantled, project category, professional subdivision, voltage level, preparation personnel, preparation time, review, review time, approval and approval Time; the project name includes the voltage level and ends with the designation of renovation, replacement or construction; 如果非可研项目是可预算的,项目工作量填报完成后导入预算数据;项目类别包括电网一次、二次系统和其他;专业细分包括输电、变电和配电;If the non-feasibility study project is budgetable, import the budget data after the project workload is completed; project category includes power grid primary system, secondary system and others; professional subdivision includes power transmission, power transformation and power distribution; 22)如果有拟拆除设备清单,则新增设备清单、或直接导入拟拆除设备或从PMS中导入,自动生成设备现状、存在问题等主体信息;22) If there is a list of equipment to be removed, add a new list of equipment, or directly import the equipment to be removed or import it from the PMS, and automatically generate the main information such as the current status of the equipment and existing problems; 拟拆除设备清单;包括“导入拆除设备”和“从PMS导入”两种导入拟拆除设备清单;List of equipment to be dismantled; including "importing dismantling equipment" and "importing from PMS" two imported lists of equipment to be dismantled; 23)对拆除设备清单中的每个设备的明细信息进行编辑,包括所属线路、设备名称、设备类型、电压等级、设备型号、投运日期、数量、计量单位、存在问题、技术实施方案、设备运行情况、安全评价、周期成本评价、效能评价;23) Edit the detailed information of each equipment in the dismantled equipment list, including the line to which it belongs, equipment name, equipment type, voltage level, equipment model, date of commissioning, quantity, unit of measurement, existing problems, technical implementation plan, equipment Operation status, safety evaluation, cycle cost evaluation, performance evaluation; 24)导入实施必要性材料、项目方案和不可测算计算表,24) Import the implementation necessary materials, project plans and non-calculated calculation tables, 25)对不可测算计算表进行量化分析,25) Quantitative analysis of non-measurable calculation tables, 量化分析的参考公式为:类似项目实际投资成本*项目投资规模的修正系数*通货膨胀率,其中,项目投资规模的修正系数=本项目投资线路长度或变电容量/类似项目投资线路长度或变电容量;The reference formula for quantitative analysis is: actual investment cost of similar projects * correction coefficient of project investment scale * inflation rate, where, correction coefficient of project investment scale = length of investment line or variable capacity of this project / length of investment line or variable capacity of similar projects capacitance; 通货膨胀率=1+类似项目至本项目之间各年度CPI之和,通货膨胀率以110%为标准。Inflation rate = 1+ the sum of CPI in each year between similar projects and this project, and the inflation rate is 110% as the standard. 3.根据权利要求1所述的基于工程量清单的电网技改工程储备管理方法,其特征在于,所述生成项目建议书并导入数据包括以下步骤:3. the method for managing power grid technical upgrading project reserves based on bill of quantities according to claim 1, characterized in that, said generating project proposal and importing data comprises the following steps: 31)生成项目建议书,定义项目建议书包括项目总投资、设备及材料合计,其中,项目总投资为设备及材料购置费、建筑工程费、安装工程费、其它费用的总和,设备及材料合计由数量×单位获取,保留小数点后两位有效数字;31) Generate a project proposal and define that the project proposal includes the total project investment, total equipment and materials, where the total project investment is the sum of equipment and material purchase fees, construction engineering fees, installation engineering fees, and other expenses, and the total equipment and materials Obtained by quantity × unit, with two valid digits after the decimal point; 32)导入数据,32) import data, 321)导出项目工单,按照查询条件导出项目汇总一览表及每个项目的项目建议书和造价单,查询条件包括基本信息、拟拆除设备信息、评估鉴定信息、附图;321) Export the project work order, export the project summary list and the project proposal and cost list of each project according to the query conditions. The query conditions include basic information, information on equipment to be removed, evaluation and identification information, and drawings; 导出格式分excel和系统.data格式,excel格式的用于用户查看,.data格式用于系统内部流转;选择导出格式为系统格式时,选择按“专业细分、单位”进行导出多个文件,并进行分发;选择按单位进行导出时,可选择按市或按县导出对应单位的多个data文件,选择按专业细分时,根据具体的细分专业导出对应的data文件;如果导出方式都不选择时,统一导出单一的data文件;导出结果分为对上上报和对下批复分别导入项目工单;The export format is divided into excel and system .data format, the excel format is used for user viewing, and the .data format is used for internal circulation in the system; when the export format is selected as the system format, select to export multiple files by "professional segmentation, unit", And distribute it; when exporting by unit, you can choose to export multiple data files of the corresponding unit by city or county; when you choose to subdivide by specialty, export the corresponding data file according to the specific subdivision; When not selected, a single data file is uniformly exported; the export results are divided into upper reporting and lower approval respectively imported into project work orders; 322)导入项目工单,选择由系统产生的data文件,解析data中存在的工单信息,选择加载所需要的工单信息。322) Import the project work order, select the data file generated by the system, analyze the work order information existing in the data, and select and load the required work order information.
CN201711190230.9A 2017-11-24 2017-11-24 Power network technology innovation project backlog control method based on bill of quantities Pending CN107705055A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711190230.9A CN107705055A (en) 2017-11-24 2017-11-24 Power network technology innovation project backlog control method based on bill of quantities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711190230.9A CN107705055A (en) 2017-11-24 2017-11-24 Power network technology innovation project backlog control method based on bill of quantities

Publications (1)

Publication Number Publication Date
CN107705055A true CN107705055A (en) 2018-02-16

Family

ID=61180917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711190230.9A Pending CN107705055A (en) 2017-11-24 2017-11-24 Power network technology innovation project backlog control method based on bill of quantities

Country Status (1)

Country Link
CN (1) CN107705055A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109359952A (en) * 2018-11-13 2019-02-19 国网四川省电力公司经济技术研究院 Method and system for reviewing bill of quantities for power transmission and transformation projects
CN109523176A (en) * 2018-11-21 2019-03-26 国网四川省电力公司凉山供电公司 A kind of power grid project budget and progress management-control method based on path analysis model
CN110097710A (en) * 2019-05-13 2019-08-06 三门核电有限公司 Wireless handset is self-service to be distributed and gives back method, wireless handset self-service diostribution device
CN111275409A (en) * 2020-02-28 2020-06-12 国网上海市电力公司 A power grid overhaul audit data processing system and processing method
CN114139736A (en) * 2021-11-17 2022-03-04 浪潮通信信息系统有限公司 Method and system for managing and controlling removal of telecommunication terminal equipment
CN114742251A (en) * 2022-04-28 2022-07-12 国网新疆电力有限公司信息通信公司 Technical improvement maintenance management system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104732034A (en) * 2015-04-01 2015-06-24 中铁隆工程集团有限公司 Constructional engineering budgeting system and working mechanism thereof
AU2016100270A4 (en) * 2013-08-19 2016-04-07 4Coflife Pty Ltd On-line interactive environment
CN106557857A (en) * 2015-09-30 2017-04-05 国家电网公司 Project of transmitting and converting electricity amount bill compilation and pricing method
CN106934546A (en) * 2017-03-13 2017-07-07 山东省计算中心(国家超级计算济南中心) The data transmission method and system of a kind of preposition estimating and examining system of Government Projects
CN108564422A (en) * 2018-05-08 2018-09-21 亳州中药材商品交易中心有限公司 A kind of system based on matrimony vine data analysis

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2016100270A4 (en) * 2013-08-19 2016-04-07 4Coflife Pty Ltd On-line interactive environment
CN104732034A (en) * 2015-04-01 2015-06-24 中铁隆工程集团有限公司 Constructional engineering budgeting system and working mechanism thereof
CN106557857A (en) * 2015-09-30 2017-04-05 国家电网公司 Project of transmitting and converting electricity amount bill compilation and pricing method
CN106934546A (en) * 2017-03-13 2017-07-07 山东省计算中心(国家超级计算济南中心) The data transmission method and system of a kind of preposition estimating and examining system of Government Projects
CN108564422A (en) * 2018-05-08 2018-09-21 亳州中药材商品交易中心有限公司 A kind of system based on matrimony vine data analysis

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
范超: "电网项目储备审核流程优化研究——以S电网公司为例", 《商业会计》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109359952A (en) * 2018-11-13 2019-02-19 国网四川省电力公司经济技术研究院 Method and system for reviewing bill of quantities for power transmission and transformation projects
CN109523176A (en) * 2018-11-21 2019-03-26 国网四川省电力公司凉山供电公司 A kind of power grid project budget and progress management-control method based on path analysis model
CN110097710A (en) * 2019-05-13 2019-08-06 三门核电有限公司 Wireless handset is self-service to be distributed and gives back method, wireless handset self-service diostribution device
CN111275409A (en) * 2020-02-28 2020-06-12 国网上海市电力公司 A power grid overhaul audit data processing system and processing method
CN114139736A (en) * 2021-11-17 2022-03-04 浪潮通信信息系统有限公司 Method and system for managing and controlling removal of telecommunication terminal equipment
CN114742251A (en) * 2022-04-28 2022-07-12 国网新疆电力有限公司信息通信公司 Technical improvement maintenance management system

Similar Documents

Publication Publication Date Title
CN107705055A (en) Power network technology innovation project backlog control method based on bill of quantities
CN107977717A (en) A method for automatically adjusting the cost difference of power grid maintenance projects
CN107123982A (en) A kind of distribution network reliability analysis method of economic benefit based on equipment alteration
CN112036953A (en) Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model
CN107967522A (en) A kind of power grid technological transformation overhaul engineering Cost Management System and its control method
CN107833108A (en) Power network technological transformation overhaul engineering bidding management control system and its control method based on bill of quantities
CN107833022A (en) Power network technology innovation project final account for completed project management method based on bill of quantities
CN108564336A (en) The identification of power transformation installing engineering construction drawing drawing and budgetary technique and system
CN107945000A (en) A kind of power grid technological transformation overhaul engineering settlement management system and its control method
CN107871212A (en) A project cost analysis method based on bill of quantities data and data model analysis technology
CN117057835A (en) Auxiliary analysis method and system for power grid engineering cost
CN104992381A (en) Power grid project quantity list evaluation application software platform establishing method
CN111882165A (en) A data splitting device and method for comprehensive project cost analysis
CN105069546A (en) Multi-service cost budget requirement data processing method for electric power enterprise
CN107798488A (en) A kind of grid maintenance engineering Stores Management System
CN107194536A (en) The power supply reliability negative benefit appraisal procedure and device of a kind of project investment
CN107705194A (en) Electricity power engineering project category Cost Comparison and Analysis method based on data analysis technique
CN111507760A (en) Method and system for screening reasonableness of bidding documents
CN114548650A (en) A cost analysis method and system for the whole life cycle of power grid assets
CN105512814A (en) Online data analysis method for material supply chain
CN104484161A (en) Model and method of provincial electric power metering center production plan prediction software system
CN106447517A (en) An imaging device for a carbon emission management system of a construction enterprise
CN107689016A (en) A kind of electricity power engineering cost historical data fusion method using data analysis technique
CN116911896A (en) A power distribution project cost analysis work data filling and reporting auxiliary system
CN116681451A (en) A zookeeper-based electricity bill simulation calculation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180216